1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
nalin [4]
3 years ago
10

Metal Shelf ​Company's standard cost for raw materials is $ 4.00 per pound and it is expected that each metal shelf uses two pou

nds of material. During October Year​ 2, 25 comma 000 pounds of materials are purchased from a new supplier for $ 97 comma 000 and 13 comma 000 shelves are produced using 27 comma 000 pounds of materials. Which statement is a possible explanation concerning the direct materials​ variances?
Business
2 answers:
pychu [463]3 years ago
8 0

Answer:

Direct material price variance

= (Standard price - Actual price) x Actual quantity purchased

=($4 - $3.38) x 25,000 pounds

= $3,000( F)

Direct material price variance is $3,000 favorable

Actual price = $97,000/25,000 pounds = $3.88

Direct material usage variance

= (Standard quantity - Actual quantity used) x Standard price

= (26,000 - 27,000) x $4

= $4,000(U)

Direct material usage variance is $4,000 unfavorable.

Standard quantity = 2 pounds x 13,000 shelves = 26,000 pounds

Explanation:

Direct material price variance is the difference between standard price and actual price multiplied by actual quantity purchased. Actual price is calculated as actual material cost divided by actual quantity purchased.

Direct material usage variance is the difference between standard quantity and actual quantity used multiplied by standard price. Standard quantity is the product of standard quantity per unit and actual unit produced.

rusak2 [61]3 years ago
6 0

Answer:

There are 3 possible primary answers:

  • a. The production department had to use more materials since the quality of the material was inferior.
  • The expectation that each metal shelf uses 2 lbs of materials is rounded off figure whereas in actual each metal shelf uses 2.0769 lbs of material
  • There is a process loss of 0.0769 of material per metal shelf's manufacturing(3.7% process loss)

Explanation:

Given:

Expected Material required per metal shelf = 2 lbs

Cost of raw material = 4 $/lb

Material purchased in Oct-year 2= 25,000 lbs

Cost of purchased material in Oct-year 2 = 97,000 $

Cost of material per lbs purchased in Oct-year 2 = 97000/25000 = 3.88 $/lb

Total shelves produced = 13,000 Nos

Total material used = 27,000 lbs

Actual material used per metal shelf = 27000/13000 = 2.0769 lbs/Nos

Thus it is concluded that either the expected materials' amount of 2 lbs was rounded off or there happened a process loss 0.0769 lbs per metal shelf.

Why not these?

Cost of material per lbs purchased in Oct-year 2 = 97000/25000 = 3.88 $/lb

b. The purchasing manager paid more than expected for materials

As the purchased lot was cheaper (@ 3.88 $/lb) than regular rate of 4$/lb therefore the purchase manager didn't pay more than expected.

c. Production workers were more efficient than anticipated

Actual material used per metal shelf = 27000/13000 = 2.0769 lbs/Nos

As the more material was used than expected thus this statement can't be true.

d. The overall materials variance is positive, no further analysis is necessary

Actual material used per metal shelf = 27000/13000 = 2.0769 lbs/Nos

Considering we are using more materials than expected so the overall material variance should not be positive and we should plan further analysis.

You might be interested in
Jamison Company developed the following reconciling information in preparing its June bank reconciliation: Cash balance per bank
Alex787 [66]

Answer:

c. $15,065

Explanation:

In bank reconciliation the book balance is adjusted using some adjustments made by the the bank and still pending by the business. We make an adjusted balance of cash book balance and bank statement balance to reconcile the amounts.

Cash balance per book 6/30    $13,000

+ Note receivable                      $4,000

- Bank charges                          $35

- NSF check                               <u>$1,900  </u>

Adjusted Cash book balance   <u>$15,065</u>

Note receivable is received in the bank but not been recorded by the business. It will be added to the balance because it will increase the balance.

Bank charges are deducted by the bank but not been recorded by the business it will be deducted.

NSF check have already added by the balance but its not been cleared. So it needs to be deducted form the Book balance.

3 0
3 years ago
You are on the team of executives at Star Bank. You have been meeting as a team to discuss the future of the bank, including big
Komok [63]

Strategic planning is the type of planning used by team of Star bank.

<h3>What is strategic planning?</h3>

Strategic planning is a type of planning that is channeled towards a purpose.

Companies make use of strategic planning to help focus on a particular goal or aim

Therefore, Strategic planning is the type of planning used by team of Star bank.

Learn more on strategic planning below

brainly.com/question/17924318

#SPJ1

7 0
2 years ago
You are considering in investing one of the two options: Investment A requires a $255,000 upfront payment from you and generates
Ainat [17]

Answer:

Option (E) Never

Explanation:

NPV from Investment Project 1 = ($255,000) + $21,000 / (r)

NPV from Investment Project 2 = ($175,000) + $29,000 / (r)

The question says that find the number of years that equals the total return which means the NPV from both investments is equal:

($255,000) + $21,000 / (r) = ($175,000) + $29,000 / (r)

$21,000 / (r) - $29,000 / (r) = $255,000 - $175,000

-$8000 / r = $80,000

r = - 8000 / 80000 = -0.01 = - 10%

The negative sign shows that project A can not make a positive NPV that will be equal to that of project B and vice versa. It can also be illustrated by putting the value of r in "NPV from Investment Project 1"

NPV from Investment Project 1 = ($255,000) + 21000 / -0.01

= ($255,000) - $210,000 = ($465,000)

This shows that the company will have to make losses of $465,000 which is not possible because company will not select projects with negative NPVs.

3 0
3 years ago
The _____ approach to systems development is a group-based tool for collecting user requirements.
miss Akunina [59]
C. prototyping, does it makes sense now.
8 0
3 years ago
What are requirements managers responsible for providing?
9966 [12]
Requirements managers are responsible for documenting and analyzing and prioritizing requirements for projects and ensuring the products or services conform to the agreed upon capabiities of these. For example, in a mine a drill contractor may be required to drill a hole of only a certain diameter and complete holes say up to 300m long and have a drill that fits inside a safety canopy provided by the client. 
5 0
3 years ago
Other questions:
  • When property rights are well defined and markets are: competitive market equilibrium violates the conditions for economic effic
    12·1 answer
  • A contingency reserve is money assigned to the project and allocated for identified risks for which contingent responses are dev
    6·1 answer
  • Juan says that good spelling, punctuation, and grammar skills are considered core responsibilities for the administrative assist
    7·2 answers
  • All of the following components are commonly found in rental housing agreements EXCEPT:
    10·1 answer
  • If the interest rate on a savings account is 0.02%, approximately how much money do you need to keep in this account for 1 year
    12·2 answers
  • What is an appropriate budgeting question
    8·1 answer
  • Use the following information to calculate cash received from dividends: Dividends revenue $ 32,300 Dividends receivable, Januar
    8·1 answer
  • The environmental protection agency of a county would like to preserve a piece of land as a wilderness area. The current owner h
    14·1 answer
  • Carlos has a small fashion company. He has been in business for a little over a year and the company looks like it is going to d
    10·2 answers
  • At a sales volume of 34,000 units, Carne Company's sales commissions (a cost that is variable with respect to sales volume) tota
    5·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!