1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Ede4ka [16]
4 years ago
8

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be run

ning very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were expecting to be only57% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,427,000 and it was done for only $1,307,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,507,000 but was actually done for $9,007,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,507,000. To date, they have spent $5,007,000 on the superstructure. Calculate the schedule variance, schedule performance index, and cost performance index for the project to dat
Business
1 answer:
Xelga [282]4 years ago
7 0

Answer:

Schedule variance = $1,105,910

Schedule performance index = 1.066

Cost performance index = 1.168

Explanation:

Note: The requirement of the question is not complete. The complete requirement is therefore provided before answering the question.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)

The explanation of the answers is now provided as follows:

Budgeted cost of work schedule = Expected cost of first activity + Expected cost of second activity + (Expected cost third activity * Expected percentage of completion) = $1,427,000 + $10,507,000 + ($8,507,000 * 57%) = $16,782,990

Budgeted cost of work performed = Expected cost of first activity + Expected cost of second activity + (Expected cost third activity * Actual percentage completed) = $1,427,000 + $10,507,000 + ($8,507,000 * 70%) = $17,888,900

Actual cost to date = Actual cost of first activity + Actual cost of second activity + Actual amount spent on third activity to date = $1,307,000 + $9,007,000 + $5,007,000 = $15,321,000

Therefore, we have:

Schedule variance = Budgeted cost of work performed - Budgeted cost of work schedule = $17,888,900 - $16,782,990 = $1,105,910

Schedule performance index = Budgeted cost of work performed / Budgeted cost of work schedule = $17,888,900 / $16,782,990 = 1.066

Cost performance index = Budgeted cost of work performed / Actual cost to date = 1.168

You might be interested in
The first step in preparing a flexible budget is to ________. identify the fixed and variable cost components prepare the budget
madam [21]

Answer:

frogfyjczkgdkdpflnchdyfj

7 0
3 years ago
7 Houseman, Inc. anticipates sales of 60,000 units, 58,000 units, 61,000 units and 60,000 units in July, August, September and O
elixir [45]

Answer:

60,500 units

Explanation:

Data provided in the question:

Month            sales

July               60,000 units

August          58,000 units

September    61,000 units

October         60,000 units

Ending inventory = 50% of the following month's sales

Now,

Total inventory required in September

= Sales in September + Ending inventory of September

= 61,000 units + 50% of sales in October

= 61,000 units + ( 0.50 × 60,000 )

= 61,000 units + 30,000 units

= 91,000 units

Number of units to be produced in September

= Total inventory required in September  - Ending inventory of August

= 91,000 units - ( 50% of 61,000 )

= 91,000 units - 30,500 units

= 60,500 units

3 0
4 years ago
Daybook Inc. budgeted production of 403,500 personal journals in 20Y6. Paper is required to produce a journal. Assume six square
Phantasy [73]

Answer:

Direct Materials    = $969,000

Direct Labor     = $699,400

Factory overhead    = $214,600

WIP       = $2,200

Finished Goods            = ($2,000)

Cost of Goods      = $1,883,200

Explanation:

Direct Materials  = $969,000

403,500 x 6 square yards = 2,421,000

2,421,000 + (40,400 - 38,900)  = 2,422,500

2,422,500 x 0.40 per square yard = $969,000

Direct Labor  = $699,400

403,500 personal journals

403,500 * 8 minutes  = 3,228,000 minutes

3,228,000/60 minutes  = 53,800

53,800 x $13.00 = $699,400

Prepare a cost of goods sold budget for Daybook Inc. using the information above

Direct Materials        = $969,000

Direct Labor         = $699,400

Factory overhead        = $214,600

WIP  ($16,500 - $14,300)     = $2,200

Finished Goods ($28,000 - $30,000)    = ($2,000)

Cost of Goods         = $1,883,200

6 0
3 years ago
Your bank offers to pay you a 3% interest rate on a one-year fixed-deposit saving account. The inflation rate is expected to be
Lubov Fominskaja [6]

Answer: By the end of the year I would be worst off

Explanation: This is because my savings would shrink ,although an interest is paid on the fixed account, the interest is not increasing at the rate at which the inflation is growing.

At any time savings don’t increase at the same rate as inflation, the owner of the fixed savings account will effectively lose money.

This is because with an increase in inflation comes a reduction in the buying power of an individual.

7 0
3 years ago
The following questions are concerned with scenarios when conventional monetary policy is ineffective – typically during and in
Stolb23 [73]

Answer:

Consider the following explanations

Explanation:

Question 2a)

Banks are required to keep some reserves with the central banks such that in case of bad times, the central bank would help the banks. However, individual banks are unable to meet the exact number of reserves after conducting their daily lending and borrowing exercises. This further leads to interbank transactions of unsecured loans. If a company defaults in the payment, then the banks associated with it, do not lend in the interbank market because the banks associated with the company will not get the repayments. This further leads to uncertainty for the other banks to lend further. There is a liquidity crunch and banks are facing difficulty in their normal functioning as there is a hindrance in loan making capabilities. As a result, the financial system freezes as no bank is willing to lend to other banks.

In this regard, the intervention of central banks becomes mandatory. The pumping of money in the market is the only way out to stabilize the tension in the interbank market. Although, the central bank intervention will cause a hole in the reserves but to stabilize the financial market is a risk that needs to be taken.

Question 2b)

When the financial system is struggling, the conventional monetary policies would lowering the interest rates, increasing the money supply and aggregate demand in the economy. Primarily three measures are:

Bank rate: It is an indirect method in creating volume in the credit and the initiative lies in the hands of commercial banks. For commercial banks, the cost of credit for the availability of credit is increased. It induces to increase consumer spending and investment made by the firms for increasing growth.

Open market Operations: It is a direct way by the central bank to induce money supply in the economy. For expansionary monetary policy, it is mainly done by selling the central bank securities in the money market for creating more liquidity in the market.

Cash Reserve ratio: The decrease in the cash reserve ratio (reserve that needs to be kept with the central banks), increases the credit of cash reserves, thereby increasing their potential to credit creating capacity.

Question 2c)

The conventional measures of central banks fail to work in times of economic crisis or deep recession because they are not able to create more money supply in the market. As a result, bank reserves are already at a minimum and cannot risk default by lowering if further. The bank interest rates are already lowered and the central banks cannot risk it bringing it to close to 0 because this will lead to a liquidity trap. Once interest rates are lowered close to zero, the economy also risks falling into a liquidity trap, where investment leads to no profits and people hoard money. As a result, the central bank needs to resort to unconventional methods.

Question 2d)

Quantitative easing is a measure that increases the money supply and lowers the long term interest rates by purchasing other securities like to buy government bonds from commercial banks. Moreover, other than bonds, the government can even buy debt instruments (mortgage-backed securities) owned by financial institutions. Quantitative easing is common with conventional monetary policies because it increases the money supply by following open market operations in the purchase and sale of bonds instead of securities and it is a direct way to do it.

On the other hand, credit easing is applied when the central banks start buying private assets such as corporate bonds.

6 0
3 years ago
Other questions:
  • Chen Inc. accepted a two-year noninterest-bearing note for $605,000 on January 1, 2021. The note was accepted as payment for mer
    12·1 answer
  • arnam Company currently produces and sells 26,000 units of a product that has a contribution margin of $9 per unit. The company
    14·1 answer
  • The use of a wrench to remove a tight nut is being discussed.
    9·1 answer
  • You own a contract that promises an annuity cash flow of $350 year-end cash flows for each of the next 3 years. (Note: The first
    15·1 answer
  • A residential property sold for $482,500. You estimate the land value to be $150,000 and the site improvements to be worth $25,0
    15·1 answer
  • The construction supervisor working with your company gives you directions to meet him at your company’s new commercial developm
    14·1 answer
  • Refer to the following lease amortization schedule. The five payments are made annually starting with the inception of the lease
    13·1 answer
  • Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts
    11·1 answer
  • Thomas Martin receives an hourly wage rate of $15, with time and a half for all hours worked in excess of 40 hours during a week
    11·1 answer
  • One who buys, stores, and resells large quantities of goods
    13·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!