1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Ede4ka [16]
3 years ago
8

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be run

ning very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were expecting to be only57% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,427,000 and it was done for only $1,307,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,507,000 but was actually done for $9,007,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,507,000. To date, they have spent $5,007,000 on the superstructure. Calculate the schedule variance, schedule performance index, and cost performance index for the project to dat
Business
1 answer:
Xelga [282]3 years ago
7 0

Answer:

Schedule variance = $1,105,910

Schedule performance index = 1.066

Cost performance index = 1.168

Explanation:

Note: The requirement of the question is not complete. The complete requirement is therefore provided before answering the question.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)

The explanation of the answers is now provided as follows:

Budgeted cost of work schedule = Expected cost of first activity + Expected cost of second activity + (Expected cost third activity * Expected percentage of completion) = $1,427,000 + $10,507,000 + ($8,507,000 * 57%) = $16,782,990

Budgeted cost of work performed = Expected cost of first activity + Expected cost of second activity + (Expected cost third activity * Actual percentage completed) = $1,427,000 + $10,507,000 + ($8,507,000 * 70%) = $17,888,900

Actual cost to date = Actual cost of first activity + Actual cost of second activity + Actual amount spent on third activity to date = $1,307,000 + $9,007,000 + $5,007,000 = $15,321,000

Therefore, we have:

Schedule variance = Budgeted cost of work performed - Budgeted cost of work schedule = $17,888,900 - $16,782,990 = $1,105,910

Schedule performance index = Budgeted cost of work performed / Budgeted cost of work schedule = $17,888,900 / $16,782,990 = 1.066

Cost performance index = Budgeted cost of work performed / Actual cost to date = 1.168

You might be interested in
Dragon Sports Inc. manufactures and sells two products, baseball bats and baseball gloves. The fixed costs are $57,000, and the
gulaghasi [49]

Answer and Explanation:

The computation is shown below:

Contribution Margin for Bat

= $50 - $50

= $0

Contribution Margin for Gloves = $100 - $80

= $20

Now  

Overall Contribution Margin = (0 ×70%) + ($20 × 30%)

= $0 + $6

= $6

Now  

A. Break even sales = Fixed cost ÷ contribution margin

= $57,000 ÷  $6

= 9,500

B.Baseball bats = 9,500 × 70% =6,650

Baseball Gloves = 9,500 × 30% = 2,850

7 0
3 years ago
problem 08-07 (algo) you are the manager of a monopolistically competitive firm, and your demand and cost functions are estimate
Ad libitum [116K]

Demand function: Q = 48 - 2P

a) 2P = 48 - Q

Therefore the inverse Demand function is

P = 24 - Q/2

b) P = 24 - Q/2

Total Revenue = PQ = (24 - Q/2)*Q

TR = 24Q - Q2/2

MR = differentiating TR with respect to Q

MR = 24 - Q

We know a firm will maximize profit at MR = MC

TC = 6 + 3Q + Q2

MC = 3 + 2Q

Putting MR = MC, we have

24 - Q = 3 + 2Q

24 - 3 = 2Q + Q

21 = 3Q

Q = 21/3 = 7

Q = 7

Putting the value of Q in the equation P = 24 - Q/2

P = 24 - 7/2

P = 24 - 3.5

P = 20.5

Therefore the profit-maximizing output is 7 and the price is $20.5

c) TR = PQ = 20.5*7 = $143.5

TC = 6 + 3Q + Q2 = 6 + 3*7 + 7*7 = 6 + 21 + 49 = $76

Profit = TR - TC = 143.5 - 76 = $67.5

Therefore the firm's maximum profit is $67.5

d) a) entry will occur until profits are zero

In the long run, more and more firms will enter the market and the economic profit will be zero in the long run.

In economics, a Demand function is a graph depicting the connection between the price of a sure commodity and the amount of that commodity that is demanded at that fee. call for curves may be used both for the price-amount courting for a person client, or for all purchasers in a selected marketplace.

Learn more about the Demand function here: brainly.com/question/24384825

#SPJ4

5 0
2 years ago
Up in Smoke Tobacco Shops' bond carries a 9 percent coupon, pays interest semiannually, and has 10 years to maturity. What is th
lara [203]

Answer:

10%

Explanation:

Since the bond is selling at a discount, it means that the coupon rate is blow the market rate, so the actual rate must be higher. Since there is only one option with an interest rate above 9%, we must check to see if it works.

10% yearly interest rate = 5% semiannual interest rate

we must determine the PV of the 20 coupons paid and the face value at maturity.

to calculate the PV of the 20 coupons ($45 each) we can use an excel spreadsheet and the NPV function with a 5% discount rate: PV of the coupons = $560.80

the PV of the face value in 10 years = $1,000 / 1.05²⁰ = $376.89

the present value of the coupons and the bond at maturity = $560.80 + $376.89 = $937.69. The PV using a 5% semiannual rate is very similar to $937.75, and since the question asked us to round up to the nearest whole percent, we can assume it is correct.

6 0
3 years ago
A decrease in the price of domestically produced industrial robots will be reflected in a. both the GDP deflator and the consume
andrezito [222]

Answer:

The correct answer is option c.

Explanation:

A consumer price index measures the change in the price level of weighted average of a basket of goods and services purchased by the consumers.  

GDP deflator measures the change in the price of all domestically produced goods and services.  

A change in the price of domestically produced industrial robots will be included in the GDP deflator as it includes the prices of all domestically produced goods and services.  

But it will not be included in the CPI as the industrial robots are not purchased by consumers in households, they are not consumer goods.

8 0
3 years ago
MB has been using proper workflow for her sales process by creating invoices, receiving payments, and recording deposits using t
Semenov [28]

She will be able to m<em>atch </em>downloaded deposits to <em>existing</em> transactions in the Banking Center.

MB been an accountant,  she must follows workflow process to ensure efficiency of operation.

  • The process of creating invoices, receiving payments, and recording deposits  are part of the Workflow process she must adhere to at her place of work.

In conclusion, the process makes the work of employee easier and uncomplicated because its enables them adhere to a strict procedure of getting work done.

Learn more about Workflow process here

<em>brainly.com/question/11939249</em>

3 0
2 years ago
Read 2 more answers
Other questions:
  • Jack owns a local trucking company. With fuel costs being expensive, Jack wants to evaluate how much fuel, on average, he should
    7·1 answer
  • The XYZ car manufacturing company is advertising its new hybrid vehicle. It understands that its competition, Toyota's hybrid ca
    13·1 answer
  • During the course of your examination of the financial statements of Trojan Corporation for the year ended December 31, 2015, yo
    9·1 answer
  • A person who invests in a business but takes no part in the day to day operations of the business is called a(n)
    9·1 answer
  • 2. Jamie Lee and Ross are estimating that they will be putting $40,000 from their savings account toward a down payment on their
    9·1 answer
  • When preparing to go shopping after the Christmas holidays, Christy actively scans the ads in the local newspaper for coupons an
    15·1 answer
  • Explain why full employment may be inconsistent with no shirking. Shirking may be likely with full employment because A. it may
    7·1 answer
  • A manufacturing company hires only welders who have completed a formal
    13·1 answer
  • g Suppose a bond is priced at $1035, has 12 years remaining until maturity, and has a 12% coupon, paid monthly. What is the amou
    10·1 answer
  • What activities can Future Educators Association members participate in? Select two options. Sporting events political rallies c
    5·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!