Answer:
$ 44000
Explanation:
Given:
Actual overhead manufacturing cost, Ac = $ 352000
Actual direct labor hours, Ah = 56000
Estimated manufacturing overhead cost, Ec = $ 330000
Estimated direct labor hour, Eh = 60000
Now,
Predetermined Overhead Rate = Ec/Eh
on substituting the values in the above formula we get
= $ 330000/60000 = 5.5
also,
Underapplied Overhead = Ac + (Ah × Predetermined Overhead Rate)
on substituting the values in the above formula we get
Underapplied Overhead = 352000 - (56000 × 5.5)
or
Underapplied Overhead = $ 44000
Explanation:
they are wide questionable buisness
Answer:
a) true
Explanation:
2/10 net 30 means that if the costumer pays within 10 days, he will be offered 2% discount, otherwise the amount is due in 30 days in full.
DSO means average number of days the company takes to receive payment from customers of credit sales.
Since the DSO of a firm given is 28 days, which is lower than the 30 days credit period normally offered by the company, therefore it may indicate that the firm's credit department is operating effectively.
Hence, answer is a) true
Answer:
the current share price is $73.31
Explanation:
The computation of the current share price is shown below:
P0 = [{D0 × (1 + g)} ÷ (1 + r1)] + [{D0 × (1 + g)^2} ÷ (1 + r1)^2] + [{D0 × (1 + g)^3} ÷ (1 + r1)^3] + [{D0 × (1 + g)^4} ÷ {(1 + r1)^3(1 + r2)}] + [{D0 × (1 + g)^5} ÷ {(1 + r1)^3(1 + r2)^2] + [{D0 × (1 + g)^6} ÷ {(1 + r1)^3(1 + r2)^3] + [{D0 × (1 + g)^7} ÷ {(rC - g)(1 + r1)^3(1 + r2)^3]
= [($4 × 1.06) ÷ 1.15] + [($4 × 1.062) ÷ 1.152] + [($4 × 1.063) ÷ 1.153] + [($4 × 1.064) ÷ (1.153 × 1.13)]
+ [($4 × 1.065) ÷ (1.153 × 1.132)] + [($4 × 1.066) ÷ (1.153 × 1.133)] + [($4 × 1.067) ÷ {(0.11 - 0.06)(1.153 × 1.133)}]
= $3.69 + $3.40 + $3.13 + $2.94 + $2.76 + $2.59 + $54.82
= $73.31
hence, the current share price is $73.31