Answer:
Weighted-average cost of treasury shares is 16 per share amounting 48 million dollars in total. (W-1)
Explanation:
(W-1) 16 * 3M i.e total number of share sold (W-1.1)
(W.1.1)
Calculations
Date Purchase Sale Closing stock WA method
12-Feb-18 2M/19/38M* 2M/19/38M
09-Jun-19 3M/14/42/M 5M/16/80M
25-May-20 3M/22/42/M 2M/16/32M
Date Purchase Sale Closing Stock FiFo method
12-Feb-18 2M/19/38M* 2M/19/38M
09-Jun-19 3M/14/42/M 2M/19/38M
3M/14/42/M
25-May-20 3M/22/42/M 2M/14/28M
*Key 2M/19/38M means 2 millions share at the rate of 19 each totaling 88 million dollars.
Answer:
Price =$1,285.71
Explanation:
<em>A perpetual bond is that which pays a fixed amount of interest income for the foreseeable future. It issuer does not always have an obligation for redemption under the terms of loan contract.</em>
The price of perpetual bond can be determined as the present value of a perpetuity. An perpetuity is an annuity that pays a fixed amount of cash flow for a certain number of years
PV = A/r
PV- price of bond- ?
A- annual interest - 45
r- Yield to maturity- 3.5%
Price = 45/0.035=1,285.714
Price =$1,285.71
Answer:
Project Size IRR
A $650,000 14.0%
B 1,050,000 13.5
C 1,000,000 11.2
D 1,200,000 11.0
Explanation:
Based on the information given the set of projects that should be accepted should be the project that has higher Internal rate of return (IRR) than the Weighted average cost of capital (WACC) percentage of 10.8% . Hence, the set of projects that should be accepted are: Project A,B,C,D
Project Size IRR
A $650,000 14.0%
B 1,050,000 13.5
C 1,000,000 11.2
D 1,200,000 11.0
Total $3,900,000
Based on the above we can see that Project A,B,C,D has a total of $3,900,000 which is higher than the retained earnings amount of $2,500,000.
Therefore the set of projects that should be accepted should be Project A,B,C,D