Answer
Directory Services
<u></u>
<u>Definition</u>
It is a type of software that is used to unify and customize the resources available at the network.
<u>Explanation</u>
This software is used to gather the information and addresses of all computers connected on the network.
It is a type of information store, where all the information related to resources (computer) and services of network has been stored. It also gives administrator rights to the single point to manage whole network resources.
This is the reason, Option "D" is the best choice for me as sole IT employ in a company. I will prefer directory services software to gather the information of all computers of organization and manage users in company.
Answer:
There is no difference between ‘’ and “” string type in python. Both are used to hold the string or sequence of character in the python. triple """ """ can also use for the same.
Example:
str1 = "aeiou"
str2 = 'aeiou'
str3 =""" hello"""
print(type(str1), type(str2),type(str3))
<class 'str'> <class 'str'> <class 'str'>
Here all are used to hold string or sequence of character.
Answer:
a=4 , b=1
Explanation:
I'm not a computer science major at all but I think I can help you with this code.
Our program wants us to add 2 to a get new a value while also subtracting 1 from b value to obtain new b value. We we want to for for as long b is not 0 and a/b is nonnegative.
One round we get:
New a=0+2=2
New b=3-1=2
Let's see if we can go another round:
New a=2+2=4
New b=2-1=1
We can't go another round because b would be negative while a is positive which would make a/b negative. So our loop stops at this 2nd round.
a=4 , b=1
Other notes:
2nd choice makes no sense because a is always going to increase because of the addition on a and b was going to decrease because of the subtraction on it.
Third choice makes no sense because a/b doesn't even exist.
Fourth choice a/b is negative not nonnegative.
Answer:
Bike Frame Flow Time
The value-added percentage of the flow time for this bike frame is:
= 46.
Explanation:
a) Data and Calculations:
Bike Frame Flow Time:
Setup time = 7 hours
Processing time = 6 hours
Storage time = 7 hours
Flow time of the bike frame = 13 hours (7 + 6)
Value-added percentage of the flow time for this bike frame = 6/13 * 100
= 46%
b) Flow time represents the amount of time a bicycle frame spends in the manufacturing process from setup to end. It is called the total processing time. Unless there is one path through the process, the flow time equals the length of the longest process path. The storage time is not included in the flow time since it is not a manufacturing process.
Answer:
I would say D hope this helps