1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
balu736 [363]
3 years ago
12

2) Dorothy types 120 words per minute. How many words does Dorothy type in

Mathematics
2 answers:
Artemon [7]3 years ago
7 0

Answer:

210 words

Step-by-step explanation:

120 x 1.75 = 210

Damm [24]3 years ago
6 0

Answer:

D (210)

Step-by-step explanation:

120 times 1.75 equals 210

You might be interested in
Sally can buy 3 pieces of candy for $1.20 or 5 pieces for $2.50, which has a better unit rate? Explain.
Julli [10]

Answer: The 3 pieces of candy- one candy under that costs only 40 cents. The five pieces separated cost 50 cents each

3 0
3 years ago
Read 2 more answers
Round 2.408 to the nearest hundredth
Verdich [7]
8 in 2.408 is closer to 10, so you round 2.408 to 2.41
7 0
4 years ago
Read 2 more answers
Let A and B be sets with cardinal numbers , n(A) = a and n(B) = b respectively . Decide whether the statement is true or false.
olya-2409 [2.1K]

Answer:

True

Step-by-step explanation:

A\cup B=A\cup(A-B)\\\\A\ and\ A-B\ are\ disjoint\ that\ means\ there\ is\ no\ common\ element\ in\ these\ two.\\\\n(A\cup B)=n(B\cup(A-B))\\\\n(A\cup B)=n(B)+n(A-B)\ \ \ \ \ \ \ as\ for\ disjoint\ set\ P,Q\ n(P\cup Q)=n(P)+n(Q)\\\\(n(P-Q)=n(P)-n(P\cap Q))\\\\n(AUB)=n(B)+n(A-B)\\\\n(AUB)=n(B)+n(A)-n(A\cap B)\\\\n(AUB)=n(A)+n(B)-n(A\cap B)\\\\Hence\ given\ statement\ is\ true

4 0
3 years ago
A masonry contractor is preparing an estimate for building a stone wall and gate. He estimates that the job will take a​ 40-hour
kodGreya [7K]

Solution: Estimated time for the work is 40 hour work week.

Estimated payment to 3 laborers working 40 hours at cost $14 per hour is:

3\times 40\times 14= $1680

Estimated payment to 6 masons working 40 hours at cost $24 per hour is:

6\times 40\times 24= $5760

Estimated cost of material = $3143

Contractor wishes to make a profit of $500

Therefore, the mathematical expression that will give the estimated cost of the job is:

Cost = 1680+5760+3143+500

The estimated total cost is:

Cost =$11083




5 0
3 years ago
Read 2 more answers
What division problem has a 1-digit divisor and 2-digit dividend and the largest possible quotient
lisov135 [29]

Answer:

99/1=99

Step-by-step explanation:

7 0
2 years ago
Other questions:
  • What is the solution set of the following system of equations?
    9·1 answer
  • Compare the given dimensions of four triangles. Which triangle is possible to construct?
    13·2 answers
  • If kelly spent $45 more on boots than she did on a pair of jeans. She spent $79.50 on the boots. How much did she spend on the j
    10·1 answer
  • Will reward brainliest
    11·1 answer
  • What is the answer and how did you figure it out??
    9·1 answer
  • Kim and leon together have $111. if kim has $17 more than leon, how much does each person have?
    14·2 answers
  • Miko can type 70 words in one minute.At that rate,how many words can he type in 12 minutes?
    8·1 answer
  • I need help from a wizard...
    15·1 answer
  • Rotation of 90 degrees counterclockwise about the origin <br><br> PLEASE ANSWER THIS QUESTION!
    7·1 answer
  • That’s why the words “Member FDIC” are so important. This indicates that your bank is covered by the federal government. If anyt
    10·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!