The minimal completion time for the activities is the shortest possible time for all the activities to be finished. In doing this, we look at the path that would require the greatest amount of time. At the START node, we choose the path that would take the longest which is 7 days leading to ACTIVITY D. Next, we choose the path leading to ACTIVITY B which takes 5 days. Then, we move to ACTIVITY C taking 5 days and finally, reach the END which would take 6 days. So, the minimal completion time is:
7 + 5 + 5 + 6 = 23 days
5/9 to chose odd card, 3/6 to roll even number
Step-by-step explanation:
You didn't give the box plot, but to obtain the percentage of people between 20 and 37 years old, first of all, find the total number of people, T. Next, find the total number of people between 20 and 37 years old, t.
Then the percentage we want to find is:
P = T/t × 100
Answer:
Step-by-step explanation:
Answer:
y can be anything smaller than x
Step-by-step explanation:
because i said it was