Answer:
True
Explanation:
Current Ratio: The current ratio shows a relationship between the current assets and the current liabilities. The formula is shown below:
Current ratio = (Total Current assets ÷ total current liabilities
)
Quick Ratio: The quick ratio shows a relationship between the quick assets and the current liabilities. The formula is shown below:
Current ratio = (Quick assets ÷ total current liabilities)
where,
Quick assets = Current assets - inventories - prepaid insurance
So, the given statement is true
The supply of the product tend to be more inelastic when the prices of the goods are high. Supply inelasticity is caused by the sudden change of the price of goods needed to release the supply and more often than not, that change of price is a price hike; meaning, the increase of price reasonable or not.
Answer:
should specialize in the production of goods for which they have a lower opportunity cost of production than their trading partners
Explanation:
A country has comparative advantage in production if it produces at a lower opportunity cost when compared to other countries.
For example, country A produces 10kg of beans and 5kg of rice. Country B produces 5kg of beans and 10kg of rice.
for country A,
opportunity cost of producing beans = 5/10 = 0.5
opportunity cost of producing rice = 10/5 = 2
for country B,
opportunity cost of producing rice = 5/10 = 0.5
opportunity cost of producing beans = 10/5 = 2
Country A has a comparative advantage in the production of beans and country B has a comparative advantage in the production of rice
Country A should specialise in the production of beans and B should specialise in the production of rice
Answer:
I belive it would be A
Explanation:
This most matches the defenition
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.