We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Answer:
a) 1/2; reduction
b) 5/4; enlargement
Step-by-step explanation:
In each case, the scale factor is CP'/CP. When it is more than 1, the dilation is an enlargement.
Even before you run the numbers, you can tell if it is an enlargement or not. If the dilated figure is larger, P is closer to C than is P'. If P' is closer to C, then it is a reduction.
a) CP'/CP = (4-2)/4 = 2/4 = 1/2 . . . . a reduction
__
b) CP'/CP = 25/20 = 5/4 . . . . an enlargement
She will have negative eight dollars. Thats all I can say