1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Aleksandr [31]
3 years ago
14

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Star

t A,B - - - A C,D 44 50 56 B D 45 60 75 C E 42 45 48 D F 31 40 49 E F 27 36 39 F End 58 70 82 What is the probability that the critical path for this project will be completed within 210 days
Mathematics
1 answer:
Doss [256]3 years ago
3 0

Answer: the probability that the critical path for this project will be completed within 210 days is 0.99725

Step-by-step explanation:

Given that;

Work break down is;  

 Time Estimates (days)

Activity  Precedes  Optimistic  Most Likely  Pessimistic  

Start          A,B              -                    -                   -  

A               C,D             44                50                 56  

B               D                45                60                  75  

C               E                42                45                   48  

D               F                31                 40                   49  

E               F                27                36                   39  

F              End            58                70                   82

we know that;

Expected Time = ( Optimistic Time + ( 4 × most likely time) + pessimistic time) / 6

and

Variance = [( pessimistic time - Optimistic time) / 6 ]²

so

ACTIVITY              EXPECTED TIME                                 VARIANCE

A                   (44 + (4 × 50) + 56) / 6 = 50                    ((56 - 44) / 6)² = 4

B                   (45 + (4 × 60) + 75) / 6 = 60                    ((75 - 45) / 6)² = 25

C                  (42 + (4 × 45) + 48) / 6 = 45                    ((48 - 42) / 6)² = 1

D                   (31 + (4 * 40) + 49) / 6 = 40                     ((49 - 31) / 6)² = 9

E                   (27 + (4 * 36) + 39) / 6 = 35                     ((39 - 27) / 6)² = 4

F                   (58 + (4 * 70) + 82) / 6 = 70                     ((82 - 58) / 6)² = 16

ACTIVITY     DURATION      ES        EF        LS        LF        SLACK

A                   50                      0        50         0         50            0

B                   60                      0        60        30        90           30

C                   45                     50       95        50        95            0

D                   40                     60      100        90       130          30

E                    35                    95       130        95       130           0

F                    70                    130     200       130      200           0

FORWARD PASS:

ES = MAXIMUM EF OF ALL PREDECESSOR ACTIVITIES; 0 IF NO PREDECESSORS ARE PRESENT.

EF = ES + DURATION OF THE ACTIVITY.

CRITICAL PATH = PATH WITH THE LONGEST COMBINED DURATION VALUE AND 0 SLACK.

CRITICAL PATH = ACEF

DURATION OF PROJECT = 200

Now the probability

VARIANCE OF CRITICAL PATH = SIGMA(VARIANCE OF THE CRITICAL PATH) = 25

STANDARD DEVIATION OF CRITICAL PATH = SQRT(VARIANCE OF CRITICAL PATH) = 5

EXPECTED TIME = DURATION OF THE PROJECT = CRITICAL PATH = 200

DUE TIME = 210

Z = (DUE TIME - EXPECTED TIME) / STANDARD DEVIATION OF CRITICAL PATH)

Z = (210 - 200) / 5 = 2

Now form the Normal Distribution Table;

Z = 0.99725

Therefore, the probability that the critical path for this project will be completed within 210 days is 0.99725

You might be interested in
Dilbert invests a total of $26,000 in two accounts paying 14% and 2% annual interest, respectively. How much was invested in eac
olganol [36]

Answer:

$17,000 at 14% and $9,000 at 2%

Step-by-step explanation:

Let x = amount invested at 14%.

Let y = amount invested at 2%.

x + y = 26000

0.14x + 0.02y = 2560

     -0.02x - 0.02y = -520

(+)    0.14x + 0.02y = 2560

-------------------------------------

       0.12x              = 2040

x = 17,000

x + y = 26000

17000 + y = 26000

y = 9000

Answer: $17,000 at 14% and $9,000 at 2%

4 0
3 years ago
ASSIGNMEN
saw5 [17]

Answer:

(-1,-8)

Step-by-step explanation:

8 0
3 years ago
Can someone help me please?
Nady [450]

Using the probability concept, the correct option of the probability of a day in May being cloudy in Sacramento is:

A. 0.43, because 13 of the 30 days were cloudy.

<h3>What is a probability?</h3>

A probability is given by the <u>number of desired outcomes divided by the number of total outcomes</u>.

For Sacramento, 30 days were considering, of which 13 days were cloudy, hence the probability of a day in May being cloudy in Sacramento is given as follows:

p = 13/30 = 0.43.

Hence the correct option is:

A. 0.43, because 13 of the 30 days were cloudy.

More can be learned about probabilities at brainly.com/question/14398287

#SPJ1

6 0
2 years ago
the length of a rectangle is 7 yd less than three times the width, and the area of the rectangle is 66 yd(squared). find the dim
Alex_Xolod [135]
So legnt=l
width=w
l=-7+3w
l=3w-7

area=66
area=legnth times width or
area=lw

subisutte
area=lw
l=3w-7
66=(3w-7)(w)
66=3w^2-7w
subtrac 66 from both sides
0=3w^2-7w-66
factor
HOW TO
multiply 3 and -66=-198
find what 2 numbers add up to -7 and multiply to get -198
the numbers area 11 and -18
so
3w^2-18w+11w-66=0
factor
(3w^2-18w)+(11w-66)=0
(3w)(w-6)+(11)(w-6)=0
factor using distributive (ab+ac=a(b+c))

(3w+11)(w-6)=0
set them to zero
3w+11=0
subtract 11
3w=-11
legnths cannot be negative so we discard this

w-6=0
add 6
w=6

width=6
legnth=3w-7
length=3(6)-7
legnt=18-7
legnth=11


width=6
legnth=11

7 0
3 years ago
I need help with this ASAP!!!!
Sedbober [7]

Answer:

wc ..3

Step-by-step explanation: prime

3 0
3 years ago
Other questions:
  • Somebody plzzzzzz help me on this
    14·1 answer
  • How many minutes are there in<br> 5/8 of 3 hours
    7·2 answers
  • Determine any data values that are missing from the table, assuming that the data represent a linear function.
    5·2 answers
  • The gravitational potential energy of an object is
    12·1 answer
  • Which phrase describes the pattern? 1, 3, 11, 123,...
    12·2 answers
  • The value of y varies directly with x, when y = 36, and x = 9. What is the equation for the relationship?
    6·2 answers
  • Find the missing factor. 5s^2+23s+24=(s+3)()
    15·1 answer
  • Decide if this statement is<br> true or false.<br> x = 2 if and only if | x1 = 2<br> A.true B. False
    14·1 answer
  • Im always having problems with this i need someone to explain please
    6·1 answer
  • S varies inversely as G. If S is 4 when G is 1.8, find S when G is 6.
    13·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!