1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Aleksandr [31]
3 years ago
14

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Star

t A,B - - - A C,D 44 50 56 B D 45 60 75 C E 42 45 48 D F 31 40 49 E F 27 36 39 F End 58 70 82 What is the probability that the critical path for this project will be completed within 210 days
Mathematics
1 answer:
Doss [256]3 years ago
3 0

Answer: the probability that the critical path for this project will be completed within 210 days is 0.99725

Step-by-step explanation:

Given that;

Work break down is;  

 Time Estimates (days)

Activity  Precedes  Optimistic  Most Likely  Pessimistic  

Start          A,B              -                    -                   -  

A               C,D             44                50                 56  

B               D                45                60                  75  

C               E                42                45                   48  

D               F                31                 40                   49  

E               F                27                36                   39  

F              End            58                70                   82

we know that;

Expected Time = ( Optimistic Time + ( 4 × most likely time) + pessimistic time) / 6

and

Variance = [( pessimistic time - Optimistic time) / 6 ]²

so

ACTIVITY              EXPECTED TIME                                 VARIANCE

A                   (44 + (4 × 50) + 56) / 6 = 50                    ((56 - 44) / 6)² = 4

B                   (45 + (4 × 60) + 75) / 6 = 60                    ((75 - 45) / 6)² = 25

C                  (42 + (4 × 45) + 48) / 6 = 45                    ((48 - 42) / 6)² = 1

D                   (31 + (4 * 40) + 49) / 6 = 40                     ((49 - 31) / 6)² = 9

E                   (27 + (4 * 36) + 39) / 6 = 35                     ((39 - 27) / 6)² = 4

F                   (58 + (4 * 70) + 82) / 6 = 70                     ((82 - 58) / 6)² = 16

ACTIVITY     DURATION      ES        EF        LS        LF        SLACK

A                   50                      0        50         0         50            0

B                   60                      0        60        30        90           30

C                   45                     50       95        50        95            0

D                   40                     60      100        90       130          30

E                    35                    95       130        95       130           0

F                    70                    130     200       130      200           0

FORWARD PASS:

ES = MAXIMUM EF OF ALL PREDECESSOR ACTIVITIES; 0 IF NO PREDECESSORS ARE PRESENT.

EF = ES + DURATION OF THE ACTIVITY.

CRITICAL PATH = PATH WITH THE LONGEST COMBINED DURATION VALUE AND 0 SLACK.

CRITICAL PATH = ACEF

DURATION OF PROJECT = 200

Now the probability

VARIANCE OF CRITICAL PATH = SIGMA(VARIANCE OF THE CRITICAL PATH) = 25

STANDARD DEVIATION OF CRITICAL PATH = SQRT(VARIANCE OF CRITICAL PATH) = 5

EXPECTED TIME = DURATION OF THE PROJECT = CRITICAL PATH = 200

DUE TIME = 210

Z = (DUE TIME - EXPECTED TIME) / STANDARD DEVIATION OF CRITICAL PATH)

Z = (210 - 200) / 5 = 2

Now form the Normal Distribution Table;

Z = 0.99725

Therefore, the probability that the critical path for this project will be completed within 210 days is 0.99725

You might be interested in
What is the length of PQ round to the nearest tenth of a unit p(-3 ,7) q(6 ,1)
elixir [45]

Answer:10.8 units

Step-by-step explanation:

3 0
3 years ago
Read 2 more answers
IMPORTANT HELP HURRY
Zanzabum
Let Bea = x
Therefore Andrew = x + 2
Chris = x - 3

Andrew * Chris = 66
(x + 2)(x - 3) = 66 Remove the brackets.
x^2 + 2x  - 3x - 6 = 66
x^2 - x - 6 = 66 Subtract 66 from both sides.
x^2 - x - 72 = 0
(x - 9)(x + 8) = 0
Find the possible values of Bea's age

x - 9 = 0
x = 9 That value works. She can be plus 9 years old.

x + 8 = 0
x = - 8. There's no way she can be - 8 years old
  
So Bea is 9. 
9 <<<<<< Answer
6 0
4 years ago
It takes 60 minutes for 7 people to paint 5 walls.
ziro4ka [17]
0.7/1 of a wall per person
3 0
3 years ago
Explanation please will give brainliest.​
Sonja [21]

Answer:

AC = 28

Step-by-step explanation:

Given

AB = 16

BC = 12

Required

Determine AC

Since A, B and C are collinear, then:

AC = AB + BC

So, we have:

AC = 16 + 12

AC = 28

5 0
3 years ago
How do you write 75% as a unreduced fraction
GarryVolchara [31]

Answer:75/100

Step-by-step explanation:

75%=75/100

8 0
3 years ago
Read 2 more answers
Other questions:
  • What multiplies to 20 and adds up to 9?
    13·2 answers
  • Give me a problem where the negative square root is not an integer please
    5·1 answer
  • SOMEONE PLEASE HELP ME ASAP PLEASE!!!​
    12·2 answers
  • What is the total price of a $40 item including 6.5% sales tax
    14·1 answer
  • How are absolute value and opposites realated​
    11·2 answers
  • Can you help me with these too?<br> its for a geometry final practice<br> plisss
    15·2 answers
  • Can you pls answer these questions?<br> I'm giving brainliest
    5·2 answers
  • If two sides of your triangle are 6cm and 18cm, what is the range of values that the third side could be?
    12·2 answers
  • Yo is arjun du.mb <br> csCsscasxsCSc
    11·2 answers
  • How do you solve this?
    7·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!