Answer:
NPV -87,259.64
Explanation:
P0 -100,000
Salvage Value 15,000
operating working capital realese 5,000
We will calculate the present value of the salvage value and the working capital realese


3,177.59

9,532.77
NPV = investment - cash flow discounted
NPV = -100,000 + 9,532.77 + 3,177.59 = -87,259.64
C) there are not enough resources to produce all of the good and services that everyone wants.
In economics, the Fisher equation is used to determine the
relationship of the nominal interest rate and the real interest rate. This
equation takes into account the effect of inflation. Mathematically this is
expressed as:
Real rate =
-1
The values given are:
Nominal rate= 10% =
0.1
Inflation=5%=0.05
Substituting known
values and by calculation:
<span>Real rate=0.0476 =
4.76%</span>
Answer:
Maximum total profit = $4,800
Explanation:
When a business is faced with a problem of shortage of a resource which can be used to produced more than one product type, to maximize the use of the resource , the business should allocate it for production purpose in such a way that it maximizes the contribution per unit of the scare resource.
Therefore the Company should allocate the budget cost to maximize the profit per production cost. This is done as follows:
Calculate the profit per budget cost and rank the product
Gasoline Heating oil
Profit per product cost 3/6=0.5 4/8= 0.5
The two products produce the same profit per dollar of cost which is $0.5. So, they are equally ranked.
So the total profit= the budget cost × profit per budget
= 9,600× $0.5 =$4,800
Maximum total profit = $4,800
Answer:
The answer is a. True.
Explanation:
During the initial stages, the members might be concerned that the project work might be difficult and this can act as a demotivating factor in the long run.
Because of this, if the manager can start the initial stages of planning of the operating methods, thus will be helpful to ease the tension and the doubts among the members.