1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Makovka662 [10]
3 years ago
15

1. It is said that a delay in critical path activity will delay the project, while a delay in a noncritical path activity will n

ot necessarily delay the project. Explain the need to specify "not necessarily."
2. Why does a project necessarily have to possess some form of deadline? What is the implication of a project without a deadline?
3. Task C has two immediate predecessors, tasks A and B. Task A has an early finish time of three days, and task B has an early finish time of five days. Task C is two days long. What is the early finish time of task C?
4. Task E has an early start time of three days and an early finish time of five days, while it also has a late start time of ten days and a late finish time of 12 days from now. What is the slack in task E?
Business
1 answer:
Taya2010 [7]3 years ago
4 0

Answer:

1. The need to specify "not necessarily" delay the project implies that the presence of positive slack or float enables a project to be completed without regard to the noncritical path activity.

2. A project necessarily possesses some form of deadline because deadlines help a project team to collaborate toward achieving the shared goal.  Another reason for a deadline is to keep complex projects on track. Deadlines also help to set project delivery expectations. Deadlines eliminate confusion in the execution of projects.  A project without a deadline looks meaningless and unimportant.

3. Task C's early finish time = 7 days.

4. The slack in task E = 2 days.

Explanation:

a) Task C's immediate predecessors = Tasks A and B

Task A's early finish time = 3 days

Task B's early finish time = 5 days

Task C's duration = 2 days

Therefore, task C's early finish time = 5 + 2 = 7 days

b) Task E's early start time = 3 days

Task E's early finish time = 5 days

Task E's late start time = 10 days

Task E's late finish time = 12 days

Slack in task E = 5 - 3 = 2 days

c) Task E can be finished in 3 days (e.g. from day 10 to day 12), but it was allocated an early completion time of 5 days.  This implies that there is a slack of 2 days.

You might be interested in
Which employment scenario would not affect the economy adversely?
spayn [35]

i not sure but cyclical makes more sense.

7 0
3 years ago
Read 2 more answers
Which one of the following types of losses is excluded from the determination of net income in income statements? Material losse
alexgriva [62]

Answer: The correct answer is "Material losses resulting from correction of errors related to prior periods.".

Explanation: It is generally established that the type of loss that is excluded from the determination of net income in the income statement are the material losses resulting from transactions in the company's investments account.

7 0
3 years ago
True or false: An EAP only contains information on what happens during an emergency.
uysha [10]
Pretty sure it’s false
5 0
3 years ago
When must you sign a deposit slip?
lesya [120]
I believe the answer is: B. <span>You only need to sign a deposit slip when receiving cash.

Deposit slip would be filled with a list of cash and cash equivalent that you give to bank teller to be added to your bank account.
Most bank provide the services which allow you to take small percentage of your deposited check in the form of cash. When doing this, you need to sign it as a form of authorization.</span><span />
4 0
3 years ago
Read 2 more answers
Causwell Company began 2018 with 11,000 units of inventory on hand. The cost of each unit was $4.00. During 2018 an additional 3
Kaylis [27]

Answer and Explanation:

For computing the cost of goods sold under two method first we have to determine the cost per unit which is shown below:

The average cost per unit is

= $108,750 ÷ 25,000 units

= $4.35

Now the cost per unit is

Total cost (11,000 units + 35,000 units) × $4.35   $200,100

Beginning units (11,000 units × $4) $44,000

The Remaining cost for 35000 units ($200,100 - $44,000)  $156,100

Divide by  Purchase cost per unit of 35000 units   $4.46

Now the cost of goods sold are as follows

1. Under the FIFO method

Beginning        11,000 × $4.00  $44,000  

Purchased        14,000 × $4.46  $62,440  

Total         25,000           $1,06,440

2. Under the LIFO method

Purchased        25,000 × $4.46  $1,11,500

4 0
3 years ago
Other questions:
  • A tornado struck the only manufacturing plant of Toledo Farm Implements (TFI) on June 1. All work-in-process inventory was destr
    13·1 answer
  • Where did newsboys live in the industrial revolution?
    14·1 answer
  • The following data concerning the retail inventory method are taken from the financial records of Sunland Company. Cost Retail B
    8·1 answer
  • Stacy has been working hard for the past week to complete the proposal her team is submitting to top management. The team’s proj
    11·1 answer
  • Suppose a car manufacturer discovers that the marginal cost of the last car produced was $15,000, while the marginal revenue was
    6·1 answer
  • Which of the following BEST describes business strategy? a strategy that assists first-line managers in making day-to-day decisi
    9·1 answer
  • You should use a(n) _____________ to track the mean diameter of the pipe for a manufacturing process producing copper pipes.
    11·1 answer
  • Both friends agree that the demand and supply for hybrid cars will increase. For each of the following situations, determine whe
    7·1 answer
  • You are planning to build a new home with approximately 2,000-2,500 gross square feet of living space on one floor. In addition,
    9·1 answer
  • Need help ASAP! Tyyyyyy
    9·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!