Answer:
$480
Explanation:
Data provided in the question:
Machine Hours Repair Costs
2,400 $6,385
1,200 $3,480
2,000 $5,285
3,400 $8,980
Now,
Machine Hours Repair Costs
Highest 3,400 $8,980
Lowest 1,200 $3,480
Difference 2,200 $5,500
Unit variable cost = $5,500 ÷ 2,200
= $2.5
Total cost at high level = $8,980
Machine hours highest level = 3,400
Also,
Total cost at high level = Fixed cost + Variable cost at highest level
or
$8,980 = Fixed cost + [ $2.5 × 3,400 ]
or
Fixed cost = $8,980 - [ $2.5 × 3,400 ]
= $8,980 - $8,500
= $480
Answer:
C. By allowing the same money to be both stored as a deposit and loaned to businesses is the correct answer.
Explanation:
Answer:
The total number of firms in this industry will decrease in the long run because increased competition will mean lower profit margins which will lead to some firms earning sub normal profits which will force them to leave the industry.
Explanation:
Answer:
40%
Explanation:
For computing the manufacturing cycle efficiency, first we have to compute the throughput time which is shown below:
Throughput time = Process time + Inspection time + Move time + Queue time
= 6 + 0.6 + 0.4 + 8
= 15
Now
Manufacturing cycle efficiency (MCE) is
= Value added time (process time) ÷ Throughput time
= 6 ÷ 15
= 40%
We simply applied the above formulas so that the manufacturing cycle efficiency (MCE) could come