Answer: A. choosing an appropriate mode for entering a particular foreign country
Explanation:
The options to the question are:
A. choosing an appropriate mode for entering a particular foreign country
B. developing a business strategy
C. marketing a product or service
D. adhering to labor and environmental standards
E. maintaining healthy relations with the U.S. government.
From the question, we are told that Sun-Jun is the executive general manager of a U.S.-based multinational corporation while Marisol is a manager in a similar position but works for an American company that operates only in the U.S. and does not engage in international business.
Since Marisol's company does not engage in international business, while Sun-Jun works in a multinational corporation, this means that the business function will be most typically exclusive to Sun-Jun will be choosing an appropriate mode for entering a particular foreign country.
The answer to this question is the letter "E" which is the "anyone in the organization". Wiki is a blog or a website where anyone in the organization is allowed to access it to view and access materials and edit it. Hence, is a team uses wikis to collaborate on a report, the editing and updating of the report should be done by anyone in the organization.
Answer:
Implementation lag
Explanation:
there are four types of lags associated with fiscal policy
Administrative lag is the time it takes to enact the needed policies. Operational lag is the time it takes for the policy to be enacted to the time the effects are felt in the economy
Recognition lag is the amount of time it takes for authorities to recognise a problem in the economy that needs fiscal policy intervention.
Implementation lag is the amount of time it takes for fiscal policy decisions to be implemented.
Answer: 0.8186
Explanation:
Given that;
activity To Tm Tp Te (V)^0.5 v
A 38 50 62 50 4 16
B 90 99 108 99 3 9
C 70 80 90 80 3.333333 11.11111
D 19 25 31 25 2 4
E 91 100 115 101 4 16
F 62 65 68 65 1 1
Expected duration Te = (4 × Tm + To + Tp ) / 6
Variance = ( Tp-To/6]²
variance of the critical path = 9+16 =25
SD of the critical path = ( var)^0.5 = 5
probability that the project will be completed within 210 days is given by
z = (210-200) / 5 = 2
which gives probability of 0.97725
Probability that the project will be completed within 195 days
z = (195-200) / 5 = -1
which corresponds to probability of 0.1586
Now required probability that project completes within 210 but before 195 days is given by
0.97725 - 0.1586 = 0.8186
Answer:
3.45%
Explanation:
the real wage at the beginning of the recession (12/07) = nominal wage / price index Dec. 2007 = $17.70 / 2.1141 = $8.3721
the real wage at the end of the recession (6/09) = nominal wage / price index June 2009 = $18.53 / 2.14527= $8.6609
% change in real wage = [($8.6609 - $8.3721) / $8.3721] x 100 = 3.44955% = 3.45%
Due to the recession, the price index changed less than the nominal wages since the inflation rate was very low. It is normal that during recessions, specially severe ones, the inflation rate decreases or even turns negative (what happened in Europe in those years).