Gain or loss from the sale of property must be calculated. The loss from foreclosure of property must be subtracted from wage income.
Based on the amount that Ramirez guaranteed the lessor and the estimated residual value, the amount to be added to the right-of-use asset is $1,434.33.
<h3>What amount should be added to the right-of-use asset?</h3>
This would be the present value of the difference between the guaranteed amount and the estimated residual value.
= 42,300 - 40,200
= $2,100
Present value:
= 2,100 / (1 + 10%)⁴
= 1,434.328
= $1,434.33
In conclusion, the right-of-use asset amount to be added is $1,434.33.
Find out more on present value at brainly.com/question/20813161.
#SPJ1
Answer:
The correct answer is $1,836,742.42.
Explanation:
According to the scenario, the given data are as follows:
EBIT = $373,000
Cost of equity = 13.2%
Tax rate = 35%
So, we can calculate the unlevered value of the firm by using following formula:
Unlevered value of the firm = EBIT × (1 - TAX RATE) ÷ COST OF EQUITY
By putting the value, we get
Unlevered value of the firm = $373,000 × ( 1 - 35%) ÷ 13.2%
= $373,000 × 0.65 ÷ 0.132
= $242,450 ÷ 0.132
= $1,836,742.42
Answer:
c) finish-to-start; start-to-start
Explanation:
Project dependencies are the time relationships between a predecessor and a successor in project management. In other words, these dependencies describe which activity among the two needs to start earlier or later and when it needs to start or finish compared to the other one.
The most common type of dependency in all projects (no matter the nature or industry) is the finish-to-start one, where the activity A needs to be completed before activity B starts, e.g. base nail polish has to be put before the top coat gets put on the nails.
The second most common type of dependency is the<em> start-to-star</em>t one, where two activities need to start at the same time. This is common for activities where synchronization is paramount.
Answer:
the value of the short forward contract is -0.49
Explanation:
the computation of the value of the short forward contract is shown below:
= (Delivery price - current forward price)× e^(risk free interest rate × no of months ÷ total number of months)
= ($42.25 - $42.75)× e^(-7.90% × 4÷12)
= -0.49
Hence, the value of the short forward contract is -0.49
Therefore the same should be considered