I believe you meant "why is the number of shifts multiplied by approximately 4.5 to obtain the total number of operators required to run the plant"
Answer and Explanation:
There are 3 shifts per day, 49 weeks per year and 5 shifts per operator per week
To get total number of operators required to run the plant, we multiply number of shifts in a year by number if operators per shift.
49 weeks×5 shifts= 245 shifts per operator per year
365×3 shifts= 1095 shifts per year
1095/245=4.5 operators per shift
total number of operators required to run the plant(per day) = 4.5×3= 13.5 approximately 14
total number of operators required to run the plant(per year) =4.5×1095=4927.5 approximately 4928
#4(1)=-1. (2)=5. (3)=14. (4)=26 srry but all i know hoped i helped
[how i did]
the first one i did 3×-5+14 which equals -1
and the second one is the same two 3×-3+14=5 you just add the the number on B
Answer: 250ft3
Step-by-step explanation:
v=l*w*H
v= 10*5 * 5
v=250
Answer:
KL = 10
Step-by-step explanation:
JK + KL = JL
2x – 2 + x – 9 = 2x + 8
Combine like terms
3x -11 = 2x+8
Subtract 2x from each side
3x-2x -11 = 2x+8-2x
x-11 = 8
Add 11 to each side
x-11+11 = 8+11
x = 19
KL = x – 9
= 19-9
= 10