Help me lol this was due last week

Mathematics
2 answers:
Tasya [4]3 years ago
8 0
The person above me is correct!
pochemuha3 years ago
3 0

Answer:

Step-by-step explanation:

1) Distribute -5 to each of the terms: -5a + 5b - 5

2) Take out the GCF which is 6y: 6y(3x + 1)

3) Distribute - 2/5: 9x - 4y

4) Take out the GCF which is 3: 3(-4d + 3e - 5)

Hope this Helps! If it doesn't, you can ask me additional questions!

You might be interested in
On Saturday mrs. armoire bought 7 pairs of socks for $3 each, and a sweater for her dog for $12. Then she found a $5 bill on the
sergeinik [125]

Answer:

She ended up with $10 less dollars then she started with

Step-by-step explanation:

3 0
3 years ago
Read 2 more answers
Can anyone help me with this question please thank you <br> Giving brainliest correct answer please
Oksi-84 [34.3K]

Answer:

1/216

Step-by-step explanation:

These are independent events because of probability of first event is not affecting the probability of another event .

probability of getting 4 on first try is 1 / 6

probability of getting six on second try is also 1 / 6 and then probability of getting more 6 on next try is again 1/6

so combined probability is 1/6 ×1/6 ×1/6= 1/216

5 0
3 years ago
Rob maintains an average monthly balance on his credit card of $1,900. His credit card company charges 21% interest annually, wh
xxMikexx [17]

Answer:

1.23

Step-by-step explanation:

1.23 - 0.01 + 0.01= 1.23

3 0
3 years ago
Which of the following is determined as a direct result of computing the earliest starting and finishing times for the activitie
Lady bird [3.3K]

Answer:

Expected project duration  is determined as a direct result of computing the earliest starting and finishing times for the activities of a project network.

Step-by-step explanation:

In project management, early start is the earliest moment at which a specific activity may start and early finish the earliest moment at which it can end. Early finish (es)  is computed as:

EF = ES + d

where d is the activity duration and ES early start

Early start is computed as

ES: Max (EF-1)

or the maximum early start of predecessory activities.

Once we have calculated these values in the network for each activity , the early finish of last activity corresponds to the expected project duration, the earliest time in which we may finish the project if there are no issues.

Max project duration is open question as we could have infinite delays or never finish the project. Time variance in project duration may only be estimated once we have actual execution times of our project.

Slack time and critical path are obtained after obtaining the ES and EF but this info alone is not sufficient. We require either the late start or the late finish of the activities to calculate slack, Zaero slack activities, those that cannot be delayed form critical path and can only be obtained after having ES. EF. LS and LF

5 0
3 years ago
Mr. Smith but seven tickets to the puppet show and spent a total of $43. Adult tickets cost nine dollars and children six ticket
AnnZ [28]

Answer:

4 kid tickets and 3 adult tickets

Step-by-step explanation:

4 x 4 = 16 + 9 x 2 = 43(?)

5 0
4 years ago
Other questions:
  • Please help me with this
    5·2 answers
  • Can u guys please help me I’m so confused on this math
    11·1 answer
  • Suppose that a triangle and a rectangle lie in plane. What is the greatest number of points at which they can intersect ?
    10·1 answer
  • I need an answer quickkk
    5·1 answer
  • Alicia has $20 in her savings account. Option one will add $50 to her account each week. Option two will double the amount in th
    10·1 answer
  • Due in 5 min please help think you
    8·2 answers
  • A quantity with an initial value of 390 the keys continuously at a rate of 5% per decade what is the value of the quantity after
    12·1 answer
  • Find mZGJH for regular octagon ABCDEFGH
    15·1 answer
  • Help omgmgmrmrr show work to also did Anthony run more or less than 11 hours?
    8·1 answer
  • This is my second time posting this can anyone help me PLZ !!
    12·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!