Answer:
Bike Frame Flow Time
The value-added percentage of the flow time for this bike frame is:
= 46.
Explanation:
a) Data and Calculations:
Bike Frame Flow Time:
Setup time = 7 hours
Processing time = 6 hours
Storage time = 7 hours
Flow time of the bike frame = 13 hours (7 + 6)
Value-added percentage of the flow time for this bike frame = 6/13 * 100
= 46%
b) Flow time represents the amount of time a bicycle frame spends in the manufacturing process from setup to end. It is called the total processing time. Unless there is one path through the process, the flow time equals the length of the longest process path. The storage time is not included in the flow time since it is not a manufacturing process.
Answer:
She can enable editing. She can change the view.
Explanation:
A process or set of rules to be followed in calculations or other problem-solving operations, especially by a computer.
Answer:
B. The account should be given a nondescript account name that cannot be easily guessed.
Answer:
item = "quesadilla"
meat = "steak"
queso = False
guacamole = False
double_meat = False
base_price = 4.5
if item == "quesadilla":
base_price = 4.0
elif item == "burrito":
base_price = 5.0
if meat == "steak" or meat == "pork":
base_price += 0.50
if meat == "steak" and double_meat:
base_price += 1.50
elif meat == "pork" and double_meat:
base_price += 1.50
elif double_meat:
base_price += 1.0
if guacamole:
base_price += 1.0
if queso and item != "nachos":
base_price += 1.0
print(base_price)
Explanation:
- Use a conditional statement to check if meat is steak or pork then add 0.50 to base_price
.
- Check if the meat is steak or pork, then double_meat adds 1.50 or 1.0 otherwise
.
-
Check if meat is steak and its double_meat
, then add 1.50 and if its for guacamole, then add 1.00 to base_price
. If queso is there and item is not nachos, add 1.00 to base_price
.
- Finally when item is nachos, no need to add any money to base_price
.