I need to see the equations to answer the question
Answer:
3 days
Step-by-step explanation:
This can be seen under Schedule management (Initiating)
Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because
Externally imposed project date = 75 days
Estimated duration of project = 75 days
Hence, a difference in these will be 0
However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration)
.
Hence the maximum float in this case will be 0 + 3 = 3 days
Answer: x = -7
Step-by-step explanation: use the slope formula and slope intercept form y = mx + b to find the equation
B is the answer show that segments WX AND YZ have equal lengths
Hello,
let's assume a the width, b the heigth.
sin 30°=a/26=1/2==>a=26/2=13 (in)
cos 30°=b/26=√3/2==>b=26*√3 / 2=13√3≈22.51666.... (in)