You have to wait for up to six months to swim after getting a nose piercing.
This is a place where people ask for their needs. I don’t think it’s cool to do these types of things
Answer:
-German unrestricted submarine warfare
Explanation:
<u>Bottom-up estimating technique</u> decomposes the work into lower, more detailed pieces.
<u>Explanation</u>:
Bottom-up estimating is the process of the estimation of work at the lowest possible level of detail. The estimates are accumulated to get the summary totals. The probability of achieving the estimated amount can be improved by building detailed cost and time estimates for a work package.
Bottom-up estimating is the project managing tool followed by many of the firms to estimate the cost and duration of project tasks. The bottom-up estimation consumes more time.