Since 1884, climate records have been kept, and they show that Philadelphia experiences an average yearly snowfall of 22.3 inches. An illustration of descriptive statistics is this value.
<h3>
What is descriptive statistics in statistics?</h3>
The fundamental characteristics of a dataset identified in a particular study are described, illustrated, and summarized using descriptive statistics. The summary provides details on the data sample and its measurements. Analysts will understand the data more readily as a result.
<h3>
What can we conclude from descriptive statistics?</h3>
The features and value distribution of one or more datasets are summarized using descriptive statistics. The central tendency and degree of value dispersion in datasets can be quickly viewed by analysts using the traditional descriptive statistics.
Learn more about descriptive statistics: brainly.com/question/13335435
#SPJ4
The Federal Reserve System, often referred to as the Federal Reserve<span> or simply "the Fed," is the central bank of the United States. It was created by the Congress to provide the nation with a safer, more flexible, and more stable monetary and financial system.
I hope my answer has come to your help. God bless and have a nice day ahead!
</span>
Debit Advertising expense $400, credit accounts payable 400.
Answer:
Two activities scheduled to be carried out in parallel and using the same scarce resource are independent.
Explanation:
An Israeli physicist named, Eliyahu M. Goldratt developed the Critical Chain Project Management (CCPM) and introduced it in his book "Critical Chain" in 1997.
The CCPM is a project management methodology used by managers to better manage a project. The CCPM ensures that the project plan is feasible and immune from any uncertainty or statistical fluctuations.
In the CCPM activity network, there are no milestones and all non-critical activities are performed as late as possible.
CCPM adopts the use of drum buffers, so as to ensure extra safety is applied to a project immediately before using constrained resource.
According to Goldratt, two activities scheduled to be carried out in parallel and using the same scarce resource are independent.