1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
poizon [28]
3 years ago
15

10-5 x a = 10 x (12+ 1/4a)

Mathematics
1 answer:
ki77a [65]3 years ago
3 0

Answer:

I hope this is helpful wish you the luck

You might be interested in
Solve the equations shown above. Show your work by using the inverse operation.​
sergeinik [125]
X=12 and x=7 hope this helps !
3 0
2 years ago
Read 2 more answers
I don’t know how to get it
Kaylis [27]

Answer:

3x+7+4x-16= 180 degrees

7x-9=180

7x=189

x= 27

yax= 3x+7

3*27+7= 81+7 = 88

4 0
3 years ago
Read 2 more answers
John can clean pools at a constant rate of 3/5 pools/hours. How many pools can John clean in 10 hours?
Ket [755]

Answer:

30/5=  6

Explicción:

Lo  utliplicas yl odivides ..m

7 0
3 years ago
What is 9 plus ten if you get it right you have to put your snap below
Ymorist [56]
21 hehehehehhehehehehehe
5 0
3 years ago
Problem 11-93 Waltner Corporation s management... Waltner Corporation's management reports that its average delivery cycle time
Marat540 [252]

Complete question is;

Waltner Corporation's management reports that its average delivery cycle time is 25 days, its average throughput time is 7.7 days, its manufacturing cycle efficiency (MCE) is 0.43, its average move time is 0.3 day, and its average queue time is 3.00 days. Required: a. What is the wait time?

b. What is the process time?

c. What is the inspection time?

Answer:

A) Wait time = 17.3 days

B) Process time = 3.311 days

C) Inspection time = 0.789 days

Step-by-step explanation:

A) we are given;

Delivery cycle time = 25 days

throughput time = 7.7 days

The formula for wait time is calculated from;

Delivery time = wait time + throughput time

So, wait time = Delivery time - throughput time

Wait time = 25 - 7.7 = 17.3 days

B) The process time is calculated from;

MCE = Process time/throughput time

So, process time = MCE x throughput time

We are given MCE = 0.43,thus, and we already know throughput time. Thus;

Process time = 0.43 x 7.7 = 3.311 days

C) The inspection time is gotten from;

throughput time = Process time + Inspection time + Move time + Queue time

Making inspection time the subject;

inspection time = throughput time - Process time - Move time - Queue time

Move time = 0.3 days

Queue time = 3 days.

Thus;

inspection time = 7.7 - 3.311 - 0.3 - 3.3 = 0.789 days

3 0
4 years ago
Other questions:
  • Which of the two functions below has the largest maximum y-value?f(x) = -3x^4 - 14g(x) = -x^3 + 2 A.There is not enough informat
    10·2 answers
  • Harry is building a model car. The actual car has a length of 15 feet and tires with a radius of 24 inches. His model car has a
    14·1 answer
  • What are the exact solutions of x2 = 5x + 2? (1 point)
    8·2 answers
  • What is the value of the expression 1 – r – a when r = 20 and a = 6?
    15·2 answers
  • SurveyMonkey is a popular website for hosting online surveys and from time to time they will also create surveys based on a subj
    14·1 answer
  • PLEASE HURRY i really need help with this
    8·1 answer
  • Find the slope of the line passing through the points (-9,5) and (-1,5)​
    11·2 answers
  • What is the LCF of 60 and 10 ?
    10·2 answers
  • One edge of a painting is 6 in. longer than the other edge. The picture has a 2-inch-wide frame. Write a quadratic function f in
    8·1 answer
  • When asked to draw a triangle with two 45 angles and a side length of 8 cm, Diego drew this triangle.
    8·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!