Historically, the average diameter of the holes drilled has been 0.25 cm and the average range has been 0.10 cm. Samples of size 4 will be collected. For the R-chart, what is the value of upper control limit
1 answer:
Solution :
Given the average range of the holes drilled = 0.10 cm
The average diameter of the holes drilled = 0.25 cm
The sample size = 4
For the sample size of 4, the factor for control limit for the range ( ) = 2.28 (From the table of constants for X-bar and R-chart)
The upper control limit for the R-chart = R-bar x
= 0.10 x 2.28
= 0.228
Therefore, the answer is greater than 0.202 but less than or equal to 0.302
You might be interested in
A = bh
12 = 4 × h [substitute A for 12 and b for h]
12 / 4 = h
3 = h
Therefore, h equals 4.
Answer:
B) car B
explanation :
I know that Car A can go at least 28 more miles than Car B. If you round 10.5 to the nearest ones place it would be 11; and if you round 12.5 to the nearest ones place it would be 13 so 13 - 11 = 2
I hope I can help you have a great day :)
Answer- 2 hours 6.50+3= 9.50 9.50•3= 28.5 54.50-28.50= 26 26/2= 13 13/ 6.50= 2
You would get $15 in total because 5x3=15.