Answer:
Results are below.
Explanation:
<u>First, we need to calculate the total cost of producing 2,900 units:</u>
Total cost= direct material + direct labor + allocated overhead
Total cost= (2*7)*2,900 + (0.5*16)*2,900 + [(0.5*16)*0.6]*2,900
Total cost= 40,600 + 23,200 + 13,920
Total cost= $77,720
<u>Now, the unitary standard cost:</u>
Unitary cost= total cost/number of units
Unitary cost= 77,720 / 2,900
Unitary cost= $26.8