1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
hoa [83]
3 years ago
15

Aaron Corporation, which has only one product, has provided the following data concerning its most recent month of operations: S

elling price $ 123 Units in beginning inventory 0 Units produced 6,600 Units sold 6,300 Units in ending inventory 300 Variable costs per unit: Direct materials $ 18 Direct labor $ 48 Variable manufacturing overhead $ 12 Variable selling and administrative expense $ 12 Fixed costs: Fixed manufacturing overhead $ 178,200 Fixed selling and administrative expense $ 25,800 What is the unit product cost for the month under variable costing?
Business
1 answer:
Arisa [49]3 years ago
8 0

Answer:

Unitary variable production cost= $78

Explanation:

Giving the following information:

Variable costs per unit:

Direct materials $ 18

Direct labor $ 48

Variable manufacturing overhead $ 12

<u>The variable costing method incorporates all variable production costs (direct material, direct labor, and variable overhead).</u>

Unitary variable production cost= 18 + 48 + 12

Unitary variable production cost= $78

You might be interested in
Ruth Richter gives a nonprofit entity $25,000 in cash. She tells the entity that it may use the gift for a particular research p
adelina 88 [10]

Answer:

The correct answer is 'Deferred Revenue'.

Explanation:

The Deferred Revenue account relates to the account in which a specific amount of payment is received in advance by the organization for the goods that are not delivered or, for the services which have not been implemented yet. They are shown on the balance sheet of the organization on the liability side.  

Thus, according to the scenario given, the Deferred revenue account will be credited, when the gift is received, but neither of the conditions is met.

6 0
3 years ago
On April 1, the company hired an attorney for a flat monthly fee of $2,000. Payment for April legal services was made by the com
docker41 [41]

Answer:

The Journal entries are as follows:

(i) On April 1,

Legal fees expenses A/c Dr.$2,000

              To Legal fees payable         $2,000

(To record the legal fees expenses)

(ii) On May 12,

Legal fees payable A/c Dr. $2,000

            To Cash A/c                          $2,000

(To record the payment of legal fees)

5 0
3 years ago
Suppose that JPMorgan Chase sells call options on $1.35 million worth of a stock portfolio with beta = 1.70. The option delta is
OlgaM077 [116]

Answer:

Particulars                         Amount                                      Explanation

Call options                        1350000  

Beta of stock                            1.7  

Delta                                      0.7  

Market change                       1%                    Implied stock change is 1.7

Stock changes by 1.7                1.19                     Implied exposure on call

                                                                                options on stock  ( ie 1.7*0.7)

Amount of exposure          1606500               Derived by multiplying

                                                                                      1.19*1,350,000

Hence market index portfolio worth $1,606,500 should be bought , however the market index portfolio trade in multiples of 1000 hence $1,607,000 worth should be obtained to hedge the exposure

Explanation:

8 0
3 years ago
Nielson Motors is considering an opportunity that requires an investment of $1,000,000 today and will provide $250,000 one year
zheka24 [161]

Answer:

The NPV is - $14958.49 . The opportunity should not be pursued as the NPV of the project discounted at the interest rate of 15% comes out to be negative . Thus, Nielson Motors should not proceed with the project.

Explanation:

To determine whether the project should be accepted or not, we need to calculate the NPV or Net Present Value of the project. If the NPV is positive, the project should be accepted.

The formula to calculate the NPV is attached.

NPV = - 1000000 + 250000 / (1 + 0.15)  +  450000 / (1 + 0.15)²  +

650000 / (1 + 0.15)³

NPV =  - $14958.49429

The opportunity should not be pursued as the NPV of the project discounted at the interest rate of 15% comes out to be negative. Thus, Nielson Motors should not proceed with the project.

7 0
4 years ago
It takes courage to kill a project, but sometimes you know it has to be done. Some common symptoms of a failing project are ill-
stellarik [79]

Solution :

a). There are several methodologies for the projects that are followed by the different companies. The successful of any project depends upon the far sightedness of the project manager and the ability of him to the execute the project in a proper order. One of the key factors that makes a project complete is the behavior of the people.

The vendors incur some excessive or some unnecessary costs to the project of they are not properly managed. The duty of the project manager is to foresee the scope of change if there is any.

If there were some additional cost and additional time for the completion of the project, then it means that it will delay the benefits of the project to others and hence attracts lower return of investments. Even though everything went according to the papers or the book, there is a lack of dedication on the project manager who believed and trusted the vendor too much.

b). A manager needs complete and clear information for an effective decision making. In any project, surprises gives a lesser amount of time and also less information related tot he project to resolve any issues that occurs at any time. It also disappoints the management that leads to spur of moment decision. So, 'Never surprise he Boss' makes a complete sentence.

c). The major factor why the project failed is the changed in the scope. The objectives are poorly cited and the timelines went overhead including the cost of the project. Too much trust of the project manager on the vendor  also lead to the schedule and the quality issues.

4 0
3 years ago
Other questions:
  • According to the trait approach to studying leadership, _____ is consistently related to leadership emergence and leadership eff
    12·1 answer
  • Which of the following statements best describes cell protection when it is first activated?
    15·2 answers
  • When sellers are willing to accept money in exchange for goods and​ services, money is acting as a?
    10·1 answer
  • How does the u.s. bureau of labor statistics gather information with regard to the typical consumption choices of americans?
    10·1 answer
  • Major E. has just opened a cooking school focusing on basic meals for new cooks. Each student pays $15 per class and receives al
    10·1 answer
  • Sheffield Co. is building a new hockey arena at a cost of $2,630,000. It received a downpayment of $520,000 from local businesse
    6·1 answer
  • In your progress report, you want the Work Completed section to follow your Summary of Costs. To
    10·1 answer
  • Complete each sentence by selecting the correct term using the drop-down list.
    13·1 answer
  • Name something that is gucci ( cool / fine / all good )
    13·1 answer
  • _____ innovations pertain to the administrative domain in an organization. Group of answer choices Technology Strategy and struc
    12·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!