Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
Answer:
The answer is "Slide Master View"
Explanation:
Slide Master Look is indeed the name of this feature. This can help you keep track of all the presentations you've created and change those ones that require work or even more information. The additional feature is the ability to change the presentation's actual picture, as it may be extended to all slides. Slide master view also allows you to change the text format & placeholders.
Answer:
scarcity
tradeoffs
Explanation:
Humans have unlimited wants and the resources available to satisfy this wants are limited. Thus, humans have to choose the most important wants and give up less important wants.
For example, if you have $20 and you want to buy a textbook , ice-cream or jeans. Each cost $20. If you need the textbook to study for a test, you would choose the book. Here $20 is the scarce resource. jeans and ice cream are what you traded off
Answer:
net income = $106,000
Explanation:
net income = total revenues - total expenses = $772,000 - $666,000 = $106,000
Any additional capital raised will increase the company's cash flows (financing activity) and any dividends distributed will decrease them (another financing activity), but they do not affect the company's net income.
Answer:
a. Accept the order
b. Increase in short-term profit of $50,000
Explanation:
<em>Note : Blowing Sand has "enough excess capacity" this means that fixed cost will be the same in the range or they will be ocurred whether or not the special order is accepted.</em>
Therefore fixed costs are Irrelevant for this decision.
<u>Incremental Costs and Revenues - accept the special order</u>
Sales ( 10,000 units × $22 each) $220,000
<em>Less</em> Variable Costs ( 10,000 units × $17each) ($170,000)
Net Income $50,000
The special order will result in an increase in short term profit of $50,000. Therefore, Blowing Sand Company should accept the order.