Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
14
Step-by-step explanation:
Answer:
there are 1,036.0 cubic inches of soil are in the plantee
i think the answer is(1,0) im not sure
Answer:
Step-by-step explanation:
you have a special triangle 30-60-90
the ration in this traingle is x, x
, 2x, where 2x is the hypothenuse
the hypothenuse is 12
x=12/2=6
the other leg is 6
=10.39