A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.
The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.
The second graph does not appropriately account for duration of predecessor tasks.
The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).
Answer:
y=-x+9
Step-by-step explanation:
Hey there! :D
None of the sides are equal. We can tell this by just looking at it. If the side BC was a straight side, it would be a right triangle, but it is not. It doesn't have any right angles.
It is a scalene triangle. It has no equal sides and no equal angles.
I hope this helps!
~kaikers
Answer:
C.
Step-by-step explanation:
Move to the right 2 units,
Move down 2 units.