Answer:
b.$39,200
Explanation:
Calculation to determine Paul's allowable itemized deductions for 2020
Using this formula
2020 itemized deductions=State income taxes+Real estate taxes+Gambling losses
Let plug in the formula
2020 itemized deductions=$13,500+$18,900+$6,800
2020 itemized deductions=$39,200
Therefore Paul's allowable itemized deductions for 2020 are $39,200
That is Importing. Option A.
Answer:The entry to record the sale will include a Credit toPaid in Capital from treasury stock at $4,000.
Explanation:
Journal entry to record sale of shares
Accounts and explanation Debit Credit
Cash $18,000
Treasury stock $14,000
Paid in Capital from Treasury STOCK $4,000
Calculation
CASH = Number of shares x Price per share
= 400 x $45=$18,000
Treasury stock = Number of shares x Price per share
= 400 x $35=$14,000
Paid In Capital = Cash - Treasury stock= $18,000- $14,000= $4000
Answer:
Option A is the cheapest.
Explanation:
Giving the following information:
The engineering department estimates costs of $450,000 for the first year. It is estimated that if process and plant alterations are made, the waste treatment cost will decline $43,000 each year. As an alternative, a specialized firm, Hydro-Clean, has offered a contract to process the waste liquids for 15 years for $225,000 per year.
We need to use the following formula and chose the smallest net present value:
NPV= Io +∑ [Cf/(1+i)^n]
Option A:
Io= 407,000
Year cost= 43,000
NPV= 734,061
Option B:
Yearly cost= 225,000
NPV= 1,936,368
The correct answer is D) maintain a uniform level of required resources.
The start of noncritical activities is delayed beyond their earliest start times (but not beyond their latest start times) in order to maintain a uniform level of required resources.
That is why companies have to establish their priorities and identify the main activities that must be accomplished on time, the people responsible to accomplish the activity, and the resources needed to successfully do so. Noncritical activities can be delayed up to a point, but the critical activities have to be followed according to the schedule.