Resources :) You’re welcome
Answer:
The correct option is A
Explanation:
In project management, earliest finish time for activity A refers to the earliest start time for succeeding activities such as B and C to start.
Assume that activities A and B comes before C, the earliest finish time for C can be arrived at by computing the earliest start-finish (critical path) of the activity with the largest EF.
That is, if two activities (A and B) come before activity C, one can estimate how long it's going to take to complete activity C if ones knows how long activity B will take (being the activity with the largest earliest finish time).
Cheers!
Answer:
8
12
Explanation:
I made the code a bit easier to understand then worked out how it would go. Here's what I did.
number = 4
repeat until number = 8:
write 2 * number
number = number + 2
Following this itenary, we have, the system first writes "8" as it multipled 4 by 2. Number is now equal to 6.
Next repetition, the system writes "12" as it multipled 6 by 2. Now, number = 8. The proccess now stops as number is now equal to 8.