Martin offers a better deal because you only have to pay 48 dollars unlike with Danny where you have to pay 105 dollars just for a 3 hr. lesson.
The answer is: "
40 cm " .
_________________________________________________________<u>Note</u>:_________________________________________________________
;
Solve for "x" (in "cm" ) ;
→ 5x = 200 * 1 ;
→ 5x = 200 ;
Divide each side of the equation by "5" ;
to isolate "x" on one side of the equation; & to solve for "x" ;
→ 5x / 5 = 200 / 5 ;
to get:
→ x = 40 .
___________________________________________________________The answer is: "
40 cm " .
___________________________________________________________
Walk through writing a general formula for the midpoint between two points. ... I believe you would simply find the differences in x and y from the midpoint to the ... if point A is at (3,2) and the midpoint is at (-2,5), i would move 5 left and 3 up from A ... do u guys think this is easy? is this the easiest thing in geometry, im trying to ...
Answer: 8 minimum work stations is what would be needed.
Step-by-step explanation:
The cycle time is computed as the operating time daily divided by the scheduled output.
It is important to note that the daily capacity of the operation layout is the operating time divided by the cycle time.
Therefore,
If you need to produce 30units/hour.
The average cycle time is as follow:
The average cycle time is the average time between the completions of units.
60/30= 2 average cycle time
=16/2
=8
8 work stations is the minimum number that would be needed.
It is important to know that in an assembly line balancing, the minimum number of work station is the ratio of the sum of all tasks time to the cycle time.