Answer:
a. Free float
Explanation:
Free float is defined as activities that are not on the critical path of project completion. There is usually a difference between their early start date and late start date.
These activities can be delayed without impacting on the project finish date.
Float is also called slack, and involves 3 tyoes: total float (difference between finsihing date of the last item on critical path and project closing date), negative float (when the expected end date of last activity is after the project closing date), and free float.
<span>The combination of all the factors that consumers evaluate when deciding whether or not to buy a good or service is called a: total product offer.
</span><span>The total product offer includes all aspects of the product , such as packaging, warranty, brand name, delivery, guarantees ...All these aspect influence the decision of the consumer.</span>
Answer
The answer and procedures of the exercise are attached in the following archives.
Explanation
You will find the procedures, formulas or necessary explanations in the archive attached below. If you have any question ask and I will aclare your doubts kindly.