Answer:
External funds needed = $40,000.
Explanation:
An increase in the firm's retained earnings (a component of the shareholder's equity) arises as a result of higher sales volume, thereby making the Asset = Liability + Shareholder's Equity Equation unbalanced.
Therefore, there must be an increment in the firm's assets by an equal amount in order to re balance the equation. If there is an increase in assets by a greater magnitude than retained earnings increment, the gap is filled by external financing (which is a liability and increases the liability component of the equation).
Net income = Sales * profit margin = $500000*10% = $50000
Dividend= Net income * payout ratio = $50000*20%= $10000
Increase in retained earnings = Net income - Dividend = $(50000-10000)
= $40000
Increase in assets = $80000
External funds needed = $(80000-40000) = $40,000.
where are the statements?
Answer:
Equity Beta = 1.1413
Explanation:
The formula to find the asset beta is
Asset Beta = Equity Beta/(1+(1-tax rate)(Debt/Equity))
We will put the values given in the question in this formula
Asset Beta = 0.8
Tax rate = 0.36
Debt = 0.40
Equity = 0.60
0.8=Equity Beta/(1+(0.64)(0.40/0.60)
0.8=Equity Beta/1+0.4266
0.8=Equity Beta/1.4266
1.4266*0.8= Equity Beta
Equity Beta = 1.1413
The answer is<u> "Identifying potentially troublesome areas so that corrective action can be taken".</u>
A budget report is an inward report utilized by the board to think about the assessed, planned projections with the real performance number accomplished amid a period.
Budgeting and financial forecasting are devices or tools that organizations use to build up an arrangement of where the executives needs to take the organization and whether it's going the correct way. Albeit budgetary determining and planning are frequently utilized together, there are particular contrasts between the two.
Answer:
Determining the priority among projects for access to the drum.
Explanation:
An Israeli physicist named, Eliyahu M. Goldratt developed the Critical Chain Project Management (CCPM) and introduced it in his book "Critical Chain" in 1997.
The CCPM is a project management methodology used by managers to better manage a project. The CCPM ensures that the project plan is feasible and immune from any uncertainty or statistical fluctuations.
In the CCPM activity network, there are no milestones and all non-critical activities are performed as late as possible.
A resource constraint can be exploited using Critical Chain Project Management (CCPM) methodology by determining the priority among projects for access to the drum (a system wide constraint).
CCPM adopts the use of drum buffers, so as to ensure extra safety is applied to a project immediately before using constrained resource.