Step-by-step explanation:
19-3.7 = 15.3 miles
hope this helps
Answer:
Principal = 3500
Time = 8 years
We are given that compound quarterly
So, No. of compounds per year = 2
Rate of interest = 5%
Formula : 
Substitute the values :


Interest = 3863.345 - 3500 = 363.345
Hence the total amount in an investment of $3500 that was compounded quarterly for 8 years at a rate of 5% is $3863.345 and the interest that was made on that account mentioned is $363.345
Answer:
Carlos graphed the perpendicular bisector of the segment that joins the two points. (a line)
Step-by-step explanation:
Carlos graphed the set of points that are equidistant from both point A and point B.
Carlos graphed the perpendicular bisector of the segment that joins the two points. (a line)
Answer:
<em>Most likely time, </em>according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
- An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
- A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
- A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
- An <em>expected time</em>, an statistical estimation.
Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":
- "[...] in as few as 15 days" is the <em>optimistic time</em>.
- "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
- "[...] but most likely will require 20 days" is the <em>most likely time</em>.
As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.