Answer:
C) 4.50 percent
Explanation:
It is given that :
Interest a corporate bond pays = 6.25 percent
The marginal percent tax bracket is given as : 28 %
We have to find the amount that the municipality bond shall pay to be the equivalent to the amount after the tax basis :
We known that the municipal bond is tax exempted after the corporate tax bond should be equal to the municipal bond to be indifferent.
Thus, rate of return = rate of return after tax = rate x (1 - tax rate)
= 6.25 % x (1 - 0.28)
= 4.50 %
Therefore the answer is = 4.50 %
Answer:
I think ot is fruit punch
Answer:
D) substantial, but not complete, performance
Explanation:
Even though Moses breached his contract with Noelle, most part of the contract was performed. The most significant part of the contract was the apartment itself, not the air conditioning system. For a material breach to exist Moses should have failed to perform in a greater way, not just the air conditioning. Probably Noelle should get a discount on the price of the apartment so that she can get the air conditioning system installed.
The fact that Noelle stopped paying for the apartment just because of this is a little overreacting. For example, if I buy a used car and the previous owner forgets to give me the spare tire, I cannot stop paying because it may be worth money but proportionally it's a small amount.
Answer:
The correct answer is letter "C": Work in Process Inventory.
Explanation:
Work in Process Inventory is an asset in the company's Balance Sheet. It represents the accumulated cost of unfinished goods that are currently in the manufacturing process. Companies that manufacture large or customer-made items typically use a work in progress inventory system to record labor, raw material, and overhead.
Answer:
40%
Explanation:
For computing the manufacturing cycle efficiency, first we have to compute the throughput time which is shown below:
Throughput time = Process time + Inspection time + Move time + Queue time
= 6 + 0.6 + 0.4 + 8
= 15
Now
Manufacturing cycle efficiency (MCE) is
= Value added time (process time) ÷ Throughput time
= 6 ÷ 15
= 40%
We simply applied the above formulas so that the manufacturing cycle efficiency (MCE) could come