Answer:
B. shortage of 1,000 gallons per week
Explanation:
Price = $1
Quantity demanded = 2,000
Quantity supplied = 1,000
Shortage = Quantity demanded - Quantity supplied
= 2,000 -1,000
= 1,000 gallons per week
Therefore, As per question Quantity demand that is 2,000 and quantity supplied that is 1,000. So, in this given case the Quantity demand is more than the quantity supplied.
Hence, there is shortage of 1,000 gallons per week.
Conducting monetary policy
Supervising and regulating depository institutions
Maintaining the stability of the financial system
The account holder tries to take out more money than the account contains.
Answer:
$33,700 (Favorable)
Explanation:
Note: Figures are not inputted. The missing figures have been figured out as below.
"<em>Nexus industries uses a standard costing system to apply manufacturing costs to its production process. In May nexus anticipated 2700 units with fixed manufacturing overhead costs allocated at $8.40 per direct labor hour with a standard of 2.5 direct labor hours per unit. In May, actual production was 3400 units and actual fixed manufacturing overhead cost were $23000. What was nexus fixed manufacturing overhead volume variance in May</em>?"
Solution:
Budgeted fixed overhead costs = Units * Direct labor cost * Standard Direct Labor hours per unit
= 2,700 units * $8.40 * 2.5
= 2,700 units * 21
= $56,700
Fixed manufacturing overhead volume variance = Actual fixed overhead cost - Budgeted fixed manufacturing overhead costs
When Actual fixed overhead = $23,000
, Budgeted fixed overhead costs = $56,700
Fixed manufacturing overhead volume variance = $23,000 - $56,700
= $33,700 (Favorable)
.
Answer:
The NPV = $1578.185602 rounded off to $1578.19
As the NPV is positive, the project should be accepted.
Explanation:
The Net Present Value or NPV is a tool used to evaluate projects. It is used with various other tools to decide whether to undertake a project or not. To calculate the Net Present Value or NPV, we take the present value of the cash inflows provided by the project and deduct the initial cost of the project. If the NPV is positive, we should proceed with the project and vice versa.
NPV = CF1 / (1+r) + CF2 / (1+r)^2 + ... + CFn / (1+r)^n - Initial Cost
Where,
- CF1, CF2, ... represents cash flow in Year 1, Year 2 and so on.
- r is the required rate of return
NPV = 3200 / (1+0.17) + 3200 (1+0.17)^2 + 3200 (1+0.17)^3 +
3200 (1+0.17)^4 + 5700 (1+0.17)^5 - 9800
NPV = $1578.185602 rounded off to $1578.19