Answer:
The correct answer is C
Explanation:
The estimate activity duration is a procedure in project management which include the analyzing of the different activities and then estimates or approximate how long it takes for accomplishing or completing the specific task with the estimated resources.
So, the estimate activity duration is the one which comprise for computing the work periods needed for completing the activities.
I believe the answer is d., the federal budget.
The answer is Action plan
(_Please give it the Brainiest answer_)
Answer and Explanation:
The computation is shown below;
Given that
Price = P = $90
And, the Marginal cost = MC = $18
a.
Now the markup would be
= (P - MC) ÷ P
= ($90 - $18) ÷ $90
= $72 ÷ $90
= 0.80
= 80%
Now the monopoly markup is
b.
As we know that
Monopoly, markup = 1 ÷ elasticity of demand(e)
e = 1 ÷ markup
= 1 ÷ 0.8
= 1.25
The absolute value of e would always be negative so e = -1.25
Therefore
The firm s price elasticity of demand is -1.25