Answer:
Step-by-step explanation:
2081.25 ; 2312.50 ; 2543.75 ; ..... 7500
a= 2081.25
d = 231.25


2081.25 + (n-1) * 231.25 = 7500
(n -1) *231.25 = 7500 - 2081.25
231.25n - 231.25 = 5418.75
231.25n = 5418.75 + 231.25
231.25n = 5650
n = 5650/231.25 = 565000/23125
n = 904/37
n = 24 years 157 days
Answer:
Option C) 146.5
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 130 weeks
Standard Deviation, σ = 10 weeks
We are given that the distribution of completion time is a bell shaped distribution that is a normal distribution.
Formula:

P(X<x) = 0.95
We have to find the value of x such that the probability is 0.95
P(X < x)
Calculation the value from standard normal z table, we have,

The project should be completed in 146.5 weeks or less.
Hence, 146.5 weeks should be set the due date such that there is a 95 percent chance that the project will be finished by this time.
8 because her are the multiples of 8:8, 16 , 24
Answer:
no
Step-by-step explanation:
because they have 2 different answers