Answer:
A
Explanation:
Free slack can be described as the total amount of time a project can be delayed without affecting the project's completion time . Tom and the contractor share a slack time of 10 days
Total slack measures the total amount of time a project can be delayed before the project's completion.
Functional slack measures the amount of time that each activity in a project can be delayed without affecting the project's completion time.
Answer: Continuous innovation
Explanation: Continuous innovation as the name suggest, means the ongoing process of innovation on a particular product or industry with slight changes in each and every stage.
The minor innovations in the latest technology overtime is called continuous innovation. Automobile and mobile phones sector are industries depicting continuous innovation.
In the given case the accounts were previously written off by debiting the Allowance for doubtful debts accounts now in order to revive these accounts receivable, we should Debit the Accounts Receivable and credit the Allowance for doubtful debts accounts. Hence the account to be credited is Allowance for doubtful debts accounts.
Hence the answer shall be Allowance for doubtful debts accounts