Minimum cycle time = time for longest task = 2.4 minutes
Maximum cycle time = sum of the times to complete all the tasks = 18 minutes
Step-by-step explanation:
For the minimum cycle time, the reasoning is that all the tasks can be done simultaneously, at some during the assembling task. Hence, minimum time to complete one cycle is the time it takes to complete task that takes the longest time to complete.
For the maximum cycle time, the reasoning here is that each task is done after the completion of the previous task. The total time taken to finish the task will then be the sum of the time taken to complete each task. This usually is at the beginning of operations.
D since the other options increase at a constant rate. For A, each increase in x is +4. For B, each increase in x is +1. For C, each increase is 13
For this question I would need the money amount what minimum might possibly be? please and thank you
I am not sure about the answer, but the formula of the prism is LxWxH
Answer:
5 people
Step-by-step explanation:
For each people Ms Hernandez bring to the zoo, she will pay $15.50, so if she go alone, 1×15.50, if she go with one person, 2×15.50, with three 3×15.50, and keep growing this way. The price each person pay is constant and equal to 15.50, and what will determine the final price is the number of people. Also remember that she always will have to pay $ 10 on parking, so you can write an equation with this:
15.50x +10 = y, as x being the number of people and y being the final price.
She have $100, so this is the max she can spend. Two know the number of people she can bring to the zoo, put 100 in place of y and find the value of x:
15.50x + 10 = 100
15.50x = 100 - 10
15.50x = 90
x = 90/15.50
x = 5.8
But there's no way to bring 0.8 person, so the max she can bring are 5 people, including her