1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
nexus9112 [7]
3 years ago
13

Plz help!!! If the prices of oranges this week is 2.89

Mathematics
1 answer:
ladessa [460]3 years ago
4 0

Answer:

I think it would be B but i'm not 100% sure

You might be interested in
In the figure below, ST = 8 and SQ = 4 Find the length of QT.
Naya [18.7K]
I belive the answer is  5 
8 0
4 years ago
Read 2 more answers
!!!!!! Pls help !!!!!
Eduardwww [97]

Answer:

\underline{\boxed{m

Step-by-step explanation:

(3x - 28) + 90 + (66 - x) = 180 \\ 2x + 128 = 180 \\ 2x = 52 \\  \boxed{x = 26} \\ m

6 0
3 years ago
Sara can complete 3/4 of a puzzle in 7/8 of an hour. How much a puzzle can she complete in an
8090 [49]

Answer:

x = 6/7 of a puzzle

Step-by-step explanation:

Number of puzzle : time taken

= 3/4 : 7/8

How much a puzzle can she complete in an hour?

Let

x = number of puzzle to complete

Number of puzzle : time taken

= x : 1

Equate both ratios to solve for x

3/4 : 7/8 = x : 1

3/4 ÷ 7/8 = x / 1

3/4 × 8/7 = x / 1

24/28 = x / 1

Cross product

24 * 1 = 28 * x

24 = 28x

x = 24/28

= 6/7

x = 6/7 of a puzzle

7 0
3 years ago
An externally imposed project completion time sets the project duration at 75 days. The critical path of the project is establis
Katen [24]

Answer:

3 days

Step-by-step explanation:

This can be seen under Schedule management (Initiating)

Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because

Externally imposed project date = 75 days

Estimated duration of project = 75 days

Hence, a difference in these will be 0

However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration) .

Hence the maximum float in this case will be 0 + 3 = 3 days

8 0
3 years ago
If the perimeter of the square is 36 cm. What is the area of the non-shaded region?
Marysya12 [62]

Answer:

either 20.25π or around 63.6173

Step-by-step explanation:

So first you find the side length of the square which is the perimeter/4 so in this case, 9. 9/2 will give you the radius of the circle and just solve for the area using the formula a=πr^2

7 0
3 years ago
Other questions:
  • 5 times 4 = 20 _ times as many as _is _
    7·1 answer
  • Gail bought 5 pounds of oranges ans 2 pounds of bananas for $14. Her husband later bought 3 pounds of oranges ans 6 pounds of ba
    11·2 answers
  • Please help answer Noah’s incorrect claim
    9·1 answer
  • Solve the combined inequality
    14·2 answers
  • Brian wants to build a ramp that leads to a storeroom 5 meters above the ground. He wants the ramp to be 10 meters long. What sh
    11·2 answers
  • (5x + 5 - 2x)(4 + 7x - 1)
    15·1 answer
  • Penny has a rectangular flower garden. The following polynomial gives the volume, V, of the garden with soil height, h.
    14·1 answer
  • Help someone please help me on tis
    13·1 answer
  • Convert the measurement.<br> 56.8 grams= ounces
    5·1 answer
  • Evaluate 8.1p + 7.9 when p = 6 and r = 7
    10·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!