Answer:
1.Allocated cost
Land 150,000
Building 250,000
Furniture 100,000
Total 500,000
2.Net income cash flow -500,000 IA
Explanation:
1.
Allocated cost
Land =500,000*180,000/600,000=150,000
Building =500,000*300,000/600,000=250,000
Furniture =500,000*120,000/600,000=100,000
Allocated cost
Land 150,000
Building 250,000
Furniture 100,000
Total 500,000
2.
Cash -500,000
Land 150,000
Building 250,000
Furniture 100,000
Net income cash flow -500,000 IA
The answer for the first question is D.
Many organization adopting a societal stance to social responsibility respond to requests for donations to Little League, Girl Scouts, and youth soccer programs.
Answer:
28%
Explanation:
let X = the percentage of ownership of Clor Confectionery
the investment account balance = $150,150 - X$20,500 + X75,650 = $165,550
$150,150 + X$55,150 = $165,550
X$55,150 = $15,400
X = $15,400 / $55,150 = 0.2792 = 27.92% ≈ 28%
Answer:
The required rate of return on stock is 14.6% and option b is the correct answer.
Explanation:
The required rate of return is the minimum return that investors demand/expect on a stock based on the systematic risk of the stock as given by the beta. The expected or required rate of return on a stock can be calculated using the CAPM equation.
The equation is,
r = rRF + Beta * (rM - rRF)
Where,
- rRF is the risk free rate
- rM is the return on market
r = 0.05 + 1.2 * (0.13 - 0.05)
r = 0.146 or 14.6%
Answer:
Early tasks opposed to later tasks.
Explanation:
Shortening is a strategic procedure used by project managers to reduce or shorten a project's duration by cutting the duration of critical path tasks.
The rationale behind shortening of a project is basically to have a competitive advantage or edge in the market. In order to compete successfully, project managers are always expected to be spontaneous in bringing their company's goods and services to the market in a flash.
There are two important ways of shortening a particular project, these are;
1. Crashing.
2. Task splitting.
In project management, the longest task is considered to be the most effective and efficient candidate activities to shorten a project's duration.
In general, the better candidates for shortening are early tasks opposed to later tasks. The early start of tasks represents one of the primary date used in project scheduling and it's the earliest date a project manager commences an activity, with respect to all its predecessors and successors.
Early tasks usually involves the use of an easy approach to project kickoff while later tasks uses the difficult approach.