Answer:
there is no picture
Step-by-step explanation:
i need to see a picture to answer this :(
Answer: 720 ways
Step-by-step explanation:
Given
A train has 1 main engine and remaining 6 train cars
If the engine is always in the front the remaining train cars can be arranged is
Area = 1/2(diagonal) * √4*side^2 - diagonal^2
Area = 1/2(16)*√(4*17^2 - 16^2)
Area = 8 * √(4*289-256)
Area = 8 *√900
Area = 8 * 30
Area = 240 m^2
The answer to 392,196=4,508
Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15