1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
slamgirl [31]
3 years ago
11

What product use programmable control?

Computers and Technology
1 answer:
Bogdan [553]3 years ago
5 0

Answer:

water tank quenching systems

You might be interested in
A binary search algorithm is written (as in the modules, for example) which searches a pre-sorted array for some user-defined va
Mazyrski [523]

Answer:

c) it will always return with an answer of 7 or fewer comparisons of data.

Explanation:

As maximum number of comparison in worst case for sorted binary search is log₂n, here n = 100, so maximum search is at least 6.6 which is approximately 7.

4 0
3 years ago
Alan is quite surprised to see that his computer has been running slower than usual. Which of the following steps or actions sho
IgorLugansk [536]
3. I believe..........
3 0
3 years ago
Read 2 more answers
What command issued from the command prompt will show the route that a packet travels from the issuing computer to another compu
svetoff [14.1K]

Answer:

B)tracert

Explanation:

Tracery Command can be regarded as

network diagnostic tool, it is used in tracking process of pathway of packet ranging from source to destination on IP network. It as well allows to know real time of each hops that are been taken by a packet as it enroutes to it's destination. The traceroute can be run by following these steps:

✓Open the run window

✓Open Command prompt, this can be done by enter "cmd" then enter.

✓ input" tracert" then destination ( Ip address or web address)

It should be noted that Tracery command issued from the command prompt will show the route that a packet travels from the issuing computer to another computer.

6 0
2 years ago
For an activity with more than one immediate predecessor activity, which of the following is used to compute its earliest finish
laila [671]

Answer:

The correct option is A

Explanation:

In project management, earliest finish time for activity A refers to the earliest start time for succeeding activities such as B and C to start.

Assume that activities A and B comes before C, the earliest finish time for C can be arrived at by computing the earliest start-finish (critical path) of the activity with the largest EF.

That is, if two activities (A and B) come before activity C, one can estimate how long it's going to take to complete activity C if ones knows how long activity B will take (being the activity with the largest earliest finish time).

Cheers!

7 0
3 years ago
Function of network security​
myrzilka [38]

Answer:ffffffffffffgggggg

Explanation:vvvc

5 0
3 years ago
Other questions:
  • To keep your emails concise and to the point
    13·1 answer
  • Which of the following applications can be used as a data source for a Microsoft® Word® mail merge? A.Outlook Contacts B.Microso
    9·2 answers
  • WHAT DOES THE TRANSPORT LAYER USE TO MAKE SURE THAT A MESSAGE IS REASSWMBLED CORRECTLY ON THE RECEIVING DEVICES?
    6·1 answer
  • An is auditor reviewing a network log discovers that an employee ran elevated commands on his/her pc by invoking the task schedu
    10·1 answer
  • Which of the following identifies the patterns used for each data series in a chart?
    13·1 answer
  • What is the simplest way to permanantly get rid of an unwanted file
    14·1 answer
  • Public class Square extends Shape{
    13·1 answer
  • FOLLOW INSTRUCTIONS BELOW , WRITTEN IN JAVA LANGUAGE PLEASE AND THANK YOU !
    10·1 answer
  • Reflection about information technology​
    11·1 answer
  • During the ___ phase of a software development project, members broadly define the features that the software should include
    15·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!