Answer: b)because near-critical paths could become critical paths with small delays in these activities
Explanation: Program evaluation and review technique(PERT) technique is used for management of the project .The organizing, maintenance,coordination of any task is done by this chart. The non-critical activities need to be observed carefully because they may create near-critical methods which can lead to complexity.
Other options are incorrect because not all activities are equally rather monitoring is done to avoid errors and slack can occur at any path . Small delays can be caused but not complete project can get delayed and there can be risk of complexity rather than being uncompleted.Thus, the correct option is option(b).
Answer:An operating system, or "OS," is software that communicates with the hardware and allows other programs to run. It is comprised of system software, or the fundamental files your computer needs to boot up and function.
Explanation:
Answer:
a.) UDP does not include data reassembly.
Answer:
The answer to this question is given below in the explanation section.
Explanation:
The selection sort algorithm step started from 0, and continue till the sorting is done.
The correct answer after selection sort algorithm at the 4th step is:D
[0,1,2,4,8,10].
The complete detail of step by step execution is shown in the attached document file.