<span>The amendment to the constitution which ended slavery in the United States of America is the thirteen amendement. The correct option is B. The thirteen amendment forbades slavery and involuntary servitude in United States of America. The amendment was passed at the end of the civil war.</span>
Hardware:
-physical parts of a computer that cause processing of data
-can be connected (physically) & can touch
- Hardware wares out during/over time
-Hardware failure is random
Software:
-A set of construction that tells a computer exactly what to do
-software is logical in nature
- dose not have an increasing failure rate
Similarities
- Behavior; Users interact with the products in various ways
- Products produce outputs and given inputs
-they have functional (user facing) and non functional (non user facing) requirements
-They are both complex (any representation of product specifications lead to a main structure)
Differences
- Software is easier to change then hardware
- Software testing is done by specialized quality assurance (QA) engineers, while hardware is done by engineers who are creating the product
-Hardware must be designed and tested to work over a range of time and environmental conditions, which is not the case for software
- Hardware designs are constrained by the need to incorporate standard parts
(Hope this helps?)
Answer:
There are multiple critical paths
Explanation:
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.
The essential technique for using CPM is to construct a model of the project that includes the following:
- A list of all activities required to complete the project (typically categorized within a work breakdown structure),
- The time (duration) that each activity will take to complete,
- The dependencies between the activities and,
- Logical end points such as milestones or deliverable items.
Using these values, CPM calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer).
considering the above function of the cpm analysis because you have multiple path, there is tendency that more than path through the project network will have zero slack values.
Answer:
if(y==10)
{
x=0; // assigning 0 to x if y equals 10.
}
else
{
x=1; // assigning 1 to x otherwise.
}
Explanation:
In the if statement i have used equal operator == which returns true if value to it's right is equal to value to it's left otherwise false.By using this operator checking value of y and if it is 10 assigning 0 to x and if it is false assigning 1 to x.
The Pirates of Silicon Valley.
Tron
Hackers
Antitrust
The Social Network
The Internship
The Imitation Game