Answer: b)because near-critical paths could become critical paths with small delays in these activities
Explanation: Program evaluation and review technique(PERT) technique is used for management of the project .The organizing, maintenance,coordination of any task is done by this chart. The non-critical activities need to be observed carefully because they may create near-critical methods which can lead to complexity.
Other options are incorrect because not all activities are equally rather monitoring is done to avoid errors and slack can occur at any path . Small delays can be caused but not complete project can get delayed and there can be risk of complexity rather than being uncompleted.Thus, the correct option is option(b).
Answer:
Explanation:
An Access Control Matrix ACM can be defined as a table that maps the permissions of a set of subjects to act upon a set of objects within a system. The matrix is a two-dimensional table with subjects down the columns and objects across the rows. The permissions of the subject to act upon a particular object are found in the cell that maps the subject to that object.
Summary
The rows correspond to the subject
The columns correspond to the object
What does each cell in the matrix contain? Answer: Each cell is the set of access rights for that subject to that object.
My sister would what’s your id