Answer:
Option C) 146.5
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 130 weeks
Standard Deviation, σ = 10 weeks
We are given that the distribution of completion time is a bell shaped distribution that is a normal distribution.
Formula:

P(X<x) = 0.95
We have to find the value of x such that the probability is 0.95
P(X < x)
Calculation the value from standard normal z table, we have,

The project should be completed in 146.5 weeks or less.
Hence, 146.5 weeks should be set the due date such that there is a 95 percent chance that the project will be finished by this time.
Answer:
4 cm
Step-by-step explanation:

Answer: the slope intercept form of 2x+y=6 is y=-2+6
Step-by-step explanation:
2x+y=6 (subtract 2x from both sides)
-2x -2x (the -2x and the 2x cancel leaving...)
<u><em>y=-2x+6</em></u> →( y equals negative two x plus six)
Answer:
B
Step-by-step explanation:
DC/AC=EC/BC
x/(x+3)=10/16
10(x+3)=16x
10x+30=16x
30=6x
x=5
DC=x=5
DC=5 units long
10/16=DE/AB, DE=y
10/16=y/10
16*y=10*10
y=6.25≈6.3
DE≈6.3