Moon Company produces baseball bats and cricket paddles. It has two departments that process all products – Cutting Department a

nd Finishing Department.
In Finishing Department, direct materials (DM) are added at the start of the process and conversion costs (CC) are added evenly during the process. Company is using Weighted Average method for the Finishing Department.

During July, beginning work in process in the Finishing Department was 80% complete as to conversion. Beginning inventories included $30,800 for transferred-in costs, $13,200 for direct materials, and $27,500 for conversion costs. Ending inventory was 30% complete as to CC. Additional information about the Finishing Department follows:



Finishing

Beginning work-in-process units

26,400

Units transferred in this period

74,800

Units completed & transferred out

79,200

Ending work-in-process units

22,000





Material costs added

$37,400

Conversion costs

$75,460

Transferred-in costs

$141,240



What is equivalent units for transferred-in cost, direct materials, and conversion cost, respectively? Separate with slash /.
Moon Company produces baseball bats and cricket paddles. It has two departments that process all products – Cutting Department and Finishing Department.

In Finishing Department, direct materials (DM) are added at the start of the process and conversion costs (CC) are added evenly during the process. Company is using Weighted Average method for the Finishing Department.

During July, beginning work in process in the Finishing Department was 80% complete as to conversion. Beginning inventories included $30,800 for transferred-in costs, $13,200 for direct materials, and $27,500 for conversion costs. Ending inventory was 30% complete as to CC. Additional information about the Finishing Department follows:



Finishing

Beginning work-in-process units

26,400

Units transferred in this period

74,800

Units completed & transferred out

79,200

Ending work-in-process units

22,000





Material costs added

$37,400

Conversion costs

$75,460

Transferred-in costs

$141,240



What is equivalent units for transferred-in cost, direct materials, and conversion cost, respectively? Separate with slash /.
Moon Company produces baseball bats and cricket paddles. It has two departments that process all products – Cutting Department and Finishing Department.

In Finishing Department, direct materials (DM) are added at the start of the process and conversion costs (CC) are added evenly during the process. Company is using Weighted Average method for the Finishing Department.

During July, beginning work in process in the Finishing Department was 80% complete as to conversion. Beginning inventories included $30,800 for transferred-in costs, $13,200 for direct materials, and $27,500 for conversion costs. Ending inventory was 30% complete as to CC. Additional information about the Finishing Department follows:



Finishing

Beginning work-in-process units

26,400

Units transferred in this period

74,800

Units completed & transferred out

79,200

Ending work-in-process units

22,000





Material costs added

$37,400

Conversion costs

$75,460

Transferred-in costs

$141,240



What is equivalent units for transferred-in cost, direct materials, and conversion cost, respectively? Separate with slash /.
Moon Company produces baseball bats and cricket paddles. It has two departments that process all products – Cutting Department and Finishing Department.

In Finishing Department, direct materials (DM) are added at the start of the process and conversion costs (CC) are added evenly during the process. Company is using Weighted Average method for the Finishing Department.

During July, beginning work in process in the Finishing Department was 80% complete as to conversion. Beginning inventories included $30,800 for transferred-in costs, $13,200 for direct materials, and $27,500 for conversion costs. Ending inventory was 30% complete as to CC. Additional information about the Finishing Department follows:



Finishing

Beginning work-in-process units

26,400

Units transferred in this period

74,800

Units completed & transferred out

79,200

Ending work-in-process units

22,000





Material costs added

$37,400

Conversion costs

$75,460

Transferred-in costs

$141,240



What is equivalent units for transferred-in cost, direct materials, and conversion cost, respectively? Separate with slash /.
Mathematics
1 answer:
Sunny_sXe [5.5K]3 years ago
4 0

The Moon Company's equivalents units for <em>transferred-in cost, direct materials, and conversion cost</em> are 74,800 / 101,200 / 86,800 respectively.

Data and Calculations:

Percentage of completion:

Beginning work in process = 80%

Ending work in process = 30%

Beginning inventories:

Transferred-in costs = $30,800

Direct materials costs = $13,200

Conversion costs = $27,500

Physical Flows of Units:

Beginning WIP = 26,400

Units transferred in from Cutting Department = 74,800

Total production units available = 101,200 (26,400 + 74,800)

Units completed and transferred out = 79,200

Ending WIP = 22,000

                                 Transferred-in   Direct Materials   Conversion

Units transferred out                                   79,200             79,200

(79,200 x 100%)

Units transferred-in         74,800                          0                      0

(74,800 x 100%)

Ending WIP                                0               22,000 (100%)   6,600 (22,000 x 30%)

Total equivalent units    74,800              101,200             86,800

Thus, the equivalent units for the Finishing Department are determined based on the percentage of completion under the Weighted Average Method.

Learn more: brainly.com/question/17078653

You might be interested in
Find g o f if f(x) = 2x - 1 and g(x) = x + 2.
bezimeni [28]

Answer:

  (g◦f)(x) = 2x +1

Step-by-step explanation:

(g◦f)(x) = g(f(x)) = g(2x -1) = (2x -1) +2

(g◦f)(x) = 2x +1

__

Substitute f(x) for the argument in the function g(x) and simplify.

7 0
4 years ago
What is the solution to the system please help
IrinaVladis [17]

Answer:

(-\frac{50}{13},-\frac{12}{13})

Step-by-step explanation:

To start, you need to find the equation of both of these lines. For the orange one, the slope can be found with the points (-5,0) and (0,-4), where there is a drop of 4 for a run of 5. This is a slope of -4/5, and a y-intercept of -4. For the purple line, you can use the points (-2,0) and (0,1), where there is a rise of 1 for a run of 2 or a slope of 1/2 and a y intercept of 1. Therefore, the two equations are:

y=-\frac{4}{5}x-4

y=\frac{1}{2}x+1

You can now set them equal to each other:

-\frac{4}{5}x-4=\frac{1}{2}x+1

Add 4 to both sides:

-\frac{4}{5}x=\frac{1}{2}x+5

Multiply both sides by 2:

-\frac{8}{5}x=x+10

Multiply both sides by 5:

-8x=5x+50

Subtract 5x from both sides:

-13x=50

Divide both sides by -13:

x=-\frac{50}{13}

y=-\frac{12}{13}

Hope this helps!

7 0
3 years ago
What is the slope of the line that contains these points?
Nikitich [7]

Answer:

-3

Step-by-step explanation:

Hope this helps:)

4 0
4 years ago
Read 2 more answers
PLEASE ANSWER ASAP!!! Using the given equation find the missing coordinates of the points and then find the slope of the line fo
Andrei [34K]

Answer:

Step-by-step explanation:A.

B.

Slope =

Step-by-step explanation:

We are given the equation of the line as .

A. The co-ordinate is given by

Substituting the value , we get,

implies  implies   i.e. 3x = -1 i.e.

Thus, the co-ordinate is .

B. The co-ordinate is given by

Substituting the value , we get,

implies  implies   i.e. 9y = 0 i.e. y= 0

Thus, the co-ordinate is .

Since, the slope of a line is given by .

We get,

Slope = .

i.e. Slope = .

i.e. Slope = .

Hence, the slope of the line is .

5 0
3 years ago
Explain how you would find the sum 46+7
worty [1.4K]


1. You would set them up:46+7

2. Next you would do 6+7 which equals 13

3. You would then bring down the 4

4. And last you get the answer:53

Hope this helped you!

5 0
3 years ago
Read 2 more answers
Other questions:
  • The answer to that problem
    15·1 answer
  • Drag and drop the constant of proportionality into the box to match the table. If the table is not proportional, drag and drop "
    13·2 answers
  • Writing expression for the calculation five times the difference of 29 and 14-11
    8·1 answer
  • The growth rate of the sunflower from day 14 to day
    15·1 answer
  • Can someone please help me ASAP​
    11·1 answer
  • Question 1<br> A<br> b<br> c<br> d <br> PLEASE HELP ASAP!!
    5·1 answer
  • I'm a brainy plus member that shows it doesn't expire until 3/2022, but when I take a picture and click on answer it won't give
    8·1 answer
  • Y= x+14 , x+ 2y= 36, find x and y and show solution pls
    7·2 answers
  • Find the greatest common factor of 90, and 135
    14·1 answer
  • Sunita performed a transformation on trapezoid LMNQ to create L′M′N′Q′, as shown in the figure below:
    8·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!