Answer:
0.5
Explanation:
Zscore = (x - mean) / standard deviation
Given the data:
X : 462 490 350 294 574
The second observation = 490
The mean and standard deviation of the data could be obtained using a calculator :
Mean = 434
standard deviation = 112
ZSCORE = (490 - 434) / 112
ZSCORE = 56 / 112
ZSCORE = 0.5
Answer:
Materials used in production go to Work in Process so;
= 936 + 1,690 + 767
= $3,393
The materials used in the general factory will go to Manufacturing Overhead.
Date Debit Credit
Jan 31 Work in Process $3,393
Manufacturing Overhead $ 667
Raw Materials Inventory $4,060
Answer:
$85
Explanation:
Costco Medical Supply's inventory:
Surgical Eq - Surgical Supp - Rehab Eq - Rehab Supp
Selling price $260 $100 $340 $165
Cost $170 $90 $250 $162
Costs to sell $30 $15 $25 $10
If we apply the net realizable value rule, the value of surgical supplies would be:
NRV = $100 = $15 = $85
the NRV is also the lower of cost since $85 < $90
The correct answer is C) 2nd Circuit or the Federal Circuit.
Princess, who resides in the 2nd Circuit, recently found a circuit court case that is favorable to her income tax research question. The circuits that she would prefer to have issued the opinion are the 2nd Circuit or the Federal Circuit.
Princess has to go to the 2nd Circuit Court of Appeals that is located in Manhattan, New York, at the Thurgood Marshall US Courthouse. It exercises federal jurisdiction in six districts of the states of Vermont, New York, and Connecticut. The 2nd Circuit Court of Appeals was established by Congress in 1891.
Answer: 0.8186
Explanation:
Given that;
activity To Tm Tp Te (V)^0.5 v
A 38 50 62 50 4 16
B 90 99 108 99 3 9
C 70 80 90 80 3.333333 11.11111
D 19 25 31 25 2 4
E 91 100 115 101 4 16
F 62 65 68 65 1 1
Expected duration Te = (4 × Tm + To + Tp ) / 6
Variance = ( Tp-To/6]²
variance of the critical path = 9+16 =25
SD of the critical path = ( var)^0.5 = 5
probability that the project will be completed within 210 days is given by
z = (210-200) / 5 = 2
which gives probability of 0.97725
Probability that the project will be completed within 195 days
z = (195-200) / 5 = -1
which corresponds to probability of 0.1586
Now required probability that project completes within 210 but before 195 days is given by
0.97725 - 0.1586 = 0.8186